170 Ind. Admin. Code 17.1-6-2

Current through November 6, 2024
Section 170 IAC 17.1-6-2 - Incentive application contents

Authority: IC 8-1-1-3; IC 8-1-37

Affected: IC 8-1-37-4

Sec. 2.

In order to be deemed complete, the incentive application of a participating electricity supplier must contain at least the following:

(1) Contact information of the electricity supplier.
(2) Total electricity measured in megawatt hours that was obtained by the electricity supplier to meet the energy requirements of its Indiana retail electric customers during the base year.
(3) Number of megawatt hours obtained each year of the CPS goal period for which the CHOICE incentive was granted from:
(A) clean energy resources:
(i) listed in IC 8-1-37-4(a);
(ii) as defined in this article; and
(iii) as may be adopted by rule by the commission;
(B) clean energy credits;
(C) Indiana clean energy sources; and
(D) clean energy resources listed in IC 8-1-37-4(a)(16) through IC 8-1-37-4(a)(21).
(4) A copy of the commission order:
(A) approving the electricity suppliers' participating in the CHOICE program; and
(B) determining what CHOICE incentive (if any) the electricity supplier should receive upon attaining each goal.
(5) Detailed explanation and supporting documentation on how the participating electricity supplier met the goal at issue. Supporting documentation may include reports from a third party tracking and trading system.
(6) Detailed explanation and supporting documentation for any variances from the electricity supplier's application plan to complete the goal.
(7) Work papers detailing all considerations and calculations in the incentive application. Each working paper must be:
(A) legible;
(B) paginated; and
(C) specifically identified.

170 IAC 17.1-6-2

Indiana Utility Regulatory Commission; 170 IAC 17.1-6-2; filed Jul 9, 2012, 3:01 p.m.: 20120808-IR-170120097FRA
Readopted filed 4/12/2018, 11:21 a.m.: 20180509-IR-170180113RFA