Section 105 IAC 13-3-5 - Work plan revisionsAuthority: IC 8-23-2-5; IC 8-23-2-6
Affected: IC 8-23-2
Sec. 5.
(a) If, before the letting date of the improvement project, the project plan is revised so that additional facility relocation work is found necessary, the: (1) department shall: (A) furnish to the utility the revised project plan under section 3 of this rule; and(B) identify to the utility the revisions within the project plan; and(2) utility shall provide to the department a revised work plan under section 3 of this rule, except that the time allowed for the utility to submit the revised work plan after receiving the revised project plan shall not exceed sixty (60) days.(b) If, after the letting date of the improvement project, additional facility relocation is found necessary, the department shall notify the utility to prepare an expedited work plan as soon as practicable for submission to the department.(c) A utility may submit a new work plan that will be considered by the department if more than one (1) year has passed since the department adopted the final work plan. The department may require the utility to proceed with the previously approved work plan.Indiana Department of Transportation; 105 IAC 13-3-5; filed Apr 14, 2008, 10:23 a.m.: 20080514-IR-105070494FRA; readopted filed Oct 2, 2013, 11:39 a.m.: 20131030-IR-105130295RFAReadopted filed 10/4/2019, 9:49 a.m.: 20191030-IR-105190422RFA