"Note: The cost of individual items of equipment of small value or of short life, including small portable tools and implements, shall not be charged to utility plant accounts unless the correctness of the accounting therefor is verified by current inventories. The cost shall be charged to the appropriate operating expense or clearing accounts, according to the use of such items, or, if such items are consumed directly in construction work, the cost shall be included as part of the cost of the construction unit.
"Allowance for funds used during construction" ('AFUDC') includes the net cost for the period of construction of borrowed funds used for construction purposes and a reasonable rate on other funds when so used, not to exceed allowances computed in accordance with the formula prescribed in paragraph (a). No AFUDC charges shall be included in these accounts upon expenditures for construction projects that have been abandoned.
A(i) = s(S/W) + d(D/(D + P + C)) (1 - S/W)
A(e) = [1 - S/W] [p(P/(D + P + C)) + c (C/(D + P + C))]
A(1) | = | Gross allowance for borrowed funds used during construction rate |
A(e) | = | Allowance for other funds used during construction rate |
S | = | Average short term debt |
s | = | Short-term debt interest rate |
D | = | Short-term debt interest rate |
d | = | Long-term debt interest rate |
P | = | Preferred stock |
p | = | Preferred stock cost rate |
C | = | Common equity |
p | = | Common equity cost rate |
W | = | Average balance in construction work in progress |
Ill. Admin. Code tit. 83, § 605.120
Amended at 22 Ill. Reg. 11742, effective July 1, 1998