At design pumping rates, a cleansing velocity of at least 2 feet per second should be maintained. Lower velocities may be permitted for very small installations. The minimum force main diameter for raw sewage shall be 4 inches except for grinder pump lift stations as allowed under Section 370.410(c)(3).
An air relief valve shall be placed at high points in the force main to prevent air locking. Vacuum relief valves may be necessary to relieve negative pressure on force mains. Force main configuration and head conditions shall be evaluated as to the need for and placement of vacuum relief valves.
Force mains should enter the gravity sewer system at a point not more than 2 feet above the flow line of the receiving manhole.
The force mains and fittings, including reaction blocking, shall be designed to withstand normal pressure and pressure surges (water hammer). The need for surge protection chambers shall be evaluated.
Force main construction near streams or water works structures and at water main crossings shall meet applicable provisions of Sections 370.125 and 370.126.
Where force mains are constructed of material which might cause the force main to be confused with potable water mains, the force main shall be appropriately identified.
Embedment bedding (haunching and initial backfill as depicted in ASTM D2321-89, Figure (1)) shall be in accordance with Section 20-2.21 A and 20.2.21 B of Standard Specifications for Water and Sewer Main Construction in Illinois, 5th ed. (1996)(no later editions or amendments).
Leakage testing shall be specified, including testing methods and leakage limits.
Ill. Admin. Code tit. 35, § 370.470
Amended at 21 Ill. Reg. 12444, effective August 28, 1997