Section 58.01.18.024 - IMPLEMENTATION OF WORK PLAN
01.Implementation. An approved work plan must be fully implemented by the applicant according to the terms and conditions of the agreement, these rules, and the Act.
02.Progress Reports. An applicant implementing a work plan must submit periodic progress reports to the Department according to the terms and conditions of the agreement.
03.Completion Report. When the applicant believes the work plan objectives were achieved and successfully implemented, the applicant must submit to the Department a work plan completion report together with a request that the Department issue a certificate of completion.
a. The completion report must contain information sufficient for the Department to determine whether the work plan objectives were achieved.
b. The Department will, within thirty (30) days of the receipt of a work plan completion report and a request for a certificate of completion, notify the applicant whether the work plan objectives were achieved.
c. If the Department notifies the applicant that the work plan objectives were not achieved, the applicant must:
i. Implement the work plan to the satisfaction of the Department; and
ii. Resubmit the work plan completion report.
d. If a work plan completion report demonstrates that the work plan objectives were achieved, the Department will certify such facts by issuing a certificate of completion. The applicant must record the certificate of completion with the deed for the site on which the remediation took place.
e. The Department may provide a certificate of completion conditioned upon continued monitoring, recordation or maintenance of institutional or engineering controls, or other continuing actions by the applicant.
f. Decisions by the Department regarding compliance with work plan completion report provisions in Subsection 024.03 are considered final agency actions.