Current through November, 2024
Section 6-74-20 - Availability of electric utility system cost data; PUC commission review(a) Any data submitted by an electric utility under §§ 6-74-17 to 6-74-19 shall be subject to review by the commission.(b) In any such review, the electric utility has the burden of coming forward with justification for its data.[Eff 2/18/82; am and comp 5/2/85; am and comp] (Auth: HRS § 269-6) (Imp: HRS § 269-27.2)