Section 3-132-6 - Value engineering sharing method

The method by which the contractor will share a portion of the cost savings from an accepted value engineering change proposal shall be in accordance with section 3-132-4 and the following:

(1) The contractor's share in cost savings shall be for the single contract only, and no consideration shall be made for future acquisition, royalty type payment, or collateral savings.
(2) The State may accept the proposed value engineering change proposal, in whole or in part. The engineer shall issue a contract change order or modify the contract to identify and describe the accepted value engineering change proposal.

Haw. Code R. § 3-132-6

[Eff NOV 17 1997] (Auth: HRS §§ 103-49, 103D-202) (Imp: HRS § 103-49)