Current through November, 2024
Section 3-122-169 - Conduct of inspections(a) Inspections or tests shall be performed so as not to unduly delay the work. The presence or absence of an inspector shall not result in the waiver of any requirements of the contract, nor shall any act, statement or omission by an inspector constitute or be deemed a change unless the procedure for changes is followed.(b) When an inspection is made in a plant or place of business, the contractor or subcontractor shall provide without charge, all reasonable facilities and assistance for the safety and convenience of the person performing the inspection or testing.(c) Inspection or testing of supplies and services performed at a plant or place of business shall be performed at reasonable times.[Eff 12/15/95; am and comp 11/17/97; comp MAR 21 2008] (Auth: HRS § 103D-202) (Imp: HRS § 103D-316)