Haw. Code R. § 11-55-15

Current through November, 2024
Section 11-55-15 - Issuance of NPDES pewits
(a) The director may issue an NPDES permit for any period not exceeding five years and may renew a permit for any additional periods not exceeding five years. The director may administratively extend the permit until the effective date of the new permit for discharges that the permit covered prior to expiration. If the director administratively extends the permit, all permit limitations and conditions remain in force and effect. Projects that do not submit a renewal NPDES application prior to the expiration date may not be administratively extended.
(b) The director shall issue or renew an NPDES permit on the following basis:
(1) The existing treatment works or waste outlet is designed, built, and equipped in accordance with:
(A) The best practicable control technology currently available or the best available technology economically achievable or the best conventional pollutant control technology for point sources other than publicly owned treatment works; and
(B) For publicly owned treatment works, secondary treatment or the best practicable waste treatment technology, so as to reduce wastes to a minimum;
(2) New treatment works or waste outlets are designed and built in compliance with the applicable standards of performance;
(3) The new or existing treatment works or waste outlet is designed and will be constructed or modified to operate without causing a violation of applicable rules of the department;
(4) The new or existing treatment works or waste outlet will not endanger the maintenance or attainment of applicable water quality standards;
(5) The facility shall comply with effluent standards and limitations, water quality standards and other requirements, as applicable in sections 11-55-19, 11-55-20, and 11-55-22; and
(6) The facility shall comply with sections 11-55-27 through 11-55-32.
(c) NPDES permits at a minimum shall include conditions and requirements at least as stringent as:
(1) Those conditions contained in sections 11-55-16, 11-55-17, 11-55-23, and 40 CFR § 122.41;
(2) The requirement that the owner or operator provide the facilities as necessary for monitoring of the authorized waste discharge into State waters and the effects of the wastes on the receiving State waters. The monitoring program shall comply with sections 11-55-28 through 11-55-32;
(3) The requirement of compliance with any applicable effluent standards and limitations, water quality standards, and other requirements imposed by the director under sections 11-55-19, 11-55-20, and 11-55-22; and
(4) Conditions requested by the Corps of Engineers and other government agencies as described in 40 CFR § 124.59.
(d) In permits where more stringent effluent limitations are included, compliance schedules may be provided in the permits if the requirements of 11-5521 and 40 CFR 122.2 and 122.47 are met.
(e) In acting upon an NPDES permit application for an individual permit the director shall deny the application unless the information submitted shows that the new or existing treatment works or waste outlet described in the NPDES permit application can, conditionally or otherwise, meet the conditions of subsection (b) or (c).
(f) Notwithstanding the provisions of subsections (a) through (e), the director shall not issue a permit or grant a modification or variance for any of the following:
(1) Discharge of any radiological or biological warfare agent, or high-level radioactive waste into State waters;
(2) Discharge which the Secretary of the Army, acting through the Chief of Engineers, finds would substantially impair anchorage and navigation;
(3) Discharge to which the regional administrator has objected in writing under any right to object provided the Administrator in Section 402(d) of the Act, 33 U.S.C. § 1342(d);
(4) Discharge from a point source which is in conflict with a plan or amendment thereto approved under Section 208(b) of the Act, 33 U.S.C. § 1288(b); or
(5) When prohibited by 40 CFR § 122.4. (g) The issuance of a permit does not convey any property rights of any sort or any exclusive privilege. The issuance of a permit does not authorize any injury to persons or property or invasion of other private rights, or any infringement of state or local law or regulations.
(h) Within 30 days from the date of issuance of the NPDES final permit, any interested party who submitted comments during the public notice period described by 40 CFR § 25.5(b) or submitted testimony in the public hearing may appeal the NPDES final permit decision issued under this chapter by filing a request for a contested case hearing, in accordance with HRS Chapter 91. "Interested" means any person with 'standing" as defined by the Hawaii Constitution, statutes, rules, and Court decisions. The appeal shall be limited to specific issues raised during the public comment period or public hearing for the NPDES permit being appealed.
(1) All publication and mailing costs associated with any public notification of any permit modification during the appeal shall be paid by the appellant to the appropriate publishing agency or agencies determined by the director. The appellant shall submit the original signed affidavit of publication to the department within four weeks of the publication date. Failure to provide and pay for public notification, as deemed appropriate by the director, is a basis to deny an appeal.
(2) Any revisions made to the permit during the appeals process shall comply with HAR 11-5516.
(i) The director may deny applications for a permit from persons who are respondents in department issued open enforcement actions associated with water pollution, who fail to make payments as required by law for permit fees or penalties, or who have a history of violating water pollution laws such as failing to comply with permit requirements, effluent limits, or enforcement orders.

Haw. Code R. § 11-55-15

[Eff 11/27/81; am and comp 10/29/92; Eff 09/23/96; am and comp 09/22/97; comp 01/06/01; am and comp 11/07/02; comp 08/01/05; am and comp 10/22/07; comp 6/15/09; comp 10/21/12; am and comp 12/6/13; am and comp 11/15/2014 ] (Auth: HRS §§ 342D-4, 342D-5, 342D-6; 33 U.S.C. §§1251, 1342, 1370) (Imp: HRS §§ 342D-2, 342D-4, 342D-5, 342D-6, 342D-50; 33 U.S.C. §§1251, 1288(b), 1342, 1370, 1251 - 1387; 40 CFR Parts 122; 123; 124, Subparts A and D; 125; §§122.4, 122.5, 122.41, 122.43, 122.44, 122.45, 122.46, 123.25(a), 124.5, 124.59)
Am and Comp 7/13/2018
Am and comp 2/9/2019
Comp OCT 22 2021
Comp 1/15/2022