Haw. Code R. § 11-54-9.1.04

Current through November, 2024
Section 11-54-9.1.04 - Water quality certification; waiver
(a) If the director fails or refuses to act on a request for certification within one year after receipt of a complete water quality certification application, then the certification requirements of section 11-54-9.1 shall be waived with respect to the federal application.
(b) If the discharge resulting from an activity receives a determination to be covered under a nationwide permit authorization, thereby fulfilling specific conditions of that permit pursuant to 33 CFR sections 330.4, 330.5, and 330.6, then the director will determine, on a case-by-case basis, which projects are considered minor and non-controversial. Certification requirements of section 11-54-9.1 shall be waived for minor and non-controversial activities within one year of receipt of a complete water quality certification application.

Haw. Code R. § 11-54-9.1.04

[Eff and comp 04/14/88; am and comp 01/18/90; am and comp 10/29/92; am and comp 04/17/00; am and comp 10/2/04; comp 06/15/09; comp 10/21/12; am and comp 12/6/13; comp 11/15/2014 ] (Auth: HRS §§ 342D-4, 342D-5, 342D-53) (Imp: HRS §§ 342D-4, 342D-5, 342D-6)