The following items shall be included in the operation plan for each phosphogypsum stack system and shall be approved by an engineer experienced in the construction and operation of phosphogypsum stacks:
Each facility shall provide the department the water balance summary sheets at the following frequency:
Each facility shall also regularly monitor water levels as required elsewhere by this rule as well as be able to demonstrate the water levels and available event, system, and maximum potential storage capacity at any time upon the request of the department.
Rainfall, inches | ||||||
Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | Total | |
Scenario 1 | 76 | 60 | 56 | 56 | 52 | 300 |
Scenario 2 | 60 | 76 | 56 | 56 | 52 | 300 |
Scenario 3 | 56 | 60 | 76 | 56 | 52 | 300 |
Scenario 4 | 52 | 56 | 60 | 76 | 56 | 300 |
Scenario 5 | 52 | 56 | 56 | 60 | 76 | 300 |
For the 100-year annual rainfall and the multi-year rainfall events, the annual rainfall quantities shall be distributed amongst the various months of the year proportionally based on the values shown for each month as listed below:
Portion of Annual Rainfall Amount, Percent | ||
100-Year Annual Rainfall | Other Multiyear Rainfall Events | |
January | 3.2 | 4.5 |
February | 3.7 | 5.2 |
March | 4.1 | 5.8 |
April | 3.4 | 4.8 |
May | 5.7 | 8.0 |
June | 15.2 | 14.8 |
July | 15.9 | 15.4 |
August | 14.5 | 14.1 |
September | 24.8 | 13.9 |
October | 4.1 | 5.8 |
November | 2.5 | 3.5 |
December | 2.9 | 4.2 |
If the water balance for any phosphogypsum stack system indicates that system storage is less than the water balance targets, the owner must provide reasonable assurance that additional process water consumption or management items, not already included as outputs in the water balance analysis, are readily available and capable of maintaining these water balance targets. Use of available storage within an AHP or RHP, up to their maximum design levels, may be used to provide this assurance. For a period not to exceed three years following July 19, 2006, a company may utilize water levels corresponding to maximum potential storage to provide reasonable assurance that water balance targets will be met. In subsequent years, if the modeling results of the annual water balance analysis provide reasonable assurance that the water balance targets will be met utilizing only system storage on or after June 1, 2011, a company may continue, at its discretion, to utilize water levels corresponding to maximum potential storage for modeled periods prior to June 1, 2011. Whenever a company relies on the use of maximum potential storage, the water balance analysis must specify the assumptions that were used to determine the temporary use of the design freeboards.
The department shall approve the plan upon a demonstration that implementation of the plan will result in achievement of the water balance targets. Upon receipt of an alternatives plan, the department shall approve or deny the alternatives plan following the procedural steps outlined in Section 120.60, F.S. Any such additional process water consumption capacity or other management items necessary to meet the terms of this paragraph shall be installed in accordance with the approved plan or within 18 months of receipt by the owner of all necessary permits or other prior approvals whichever occurs later.
Fla. Admin. Code Ann. R. 62-672.780
Rulemaking Authority 403.4155 FS. Law Implemented 403.4155 FS.
New 6-28-99, Amended 7-19-06.