An applicant shall submit permit application materials to the Permit Processing Division of the Department of Consumer and Regulatory Affairs (DCRA) for transmittal to the Mayor's Agent pursuant to the Act as further described in Chapter 3.
Upon receipt of the permit application and the results of any required review by the Commission of Fine Arts, the HPO shall review the application under the authority delegated in § 321, and take action as appropriate.
If the application does not meet the requirements of this chapter, and the HPO is not able to resolve the deficiencies directly with the applicant, the HPO shall prepare the case for review by the Board as provided in Chapter 3.
D.C. Mun. Regs. tit. 10, r. 10-C2502