Conn. Agencies Regs. § 29-232-33

Current through November 7, 2024
Section 29-232-33 - Preparation of boilers for inspection

All boilers, unless otherwise exempt by statute, which are subject to regular inspections, shall be prepared for such inspections or hydrostatic tests whenever necessary by the owner or user when notified by an inspector. The owner or user shall prepare each boiler for internal inspection and shall prepare for and apply the hydrostatic test whenever necessary, on the date specified by an inspector, which date shall be not less than seven days after the date of notification.

Conn. Agencies Regs. § 29-232-33

Effective August 25, 1987