Conn. Agencies Regs. § 16a-32-6

Current through December 4, 2024
Section 16a-32-6 - Committee approves or does not approve interim change: Notification
(a) Within thirty (30) calendar days of receipt of the Secretary's report and recommendations, the Committee shall decide to approve or not to approve the proposed interim change and shall so inform the Secretary not more than ten (10) days after such decision.
(b) The Secretary shall make the interim change on master copies of the Policies Plan, including the map, if pertinent, recording the date, month and year of such action in its records.
(c) The Secretary shall set an effective date for the interim change to take effect no later than ten (10) days from receipt of the Committee's action.
(d) The Secretary shall advise the applicant by registered letter of the action by the Committee and citing the effective date. Notices shall also be sent to the appropriate political subdivision(s) and regional planning agency(s) or agency(s) with the powers of a regional planning agency.
(e) In the case of approval of an interim change, the Secretary shall send notification of such action with a brief description and effective date for publication in the Connecticut Law Journal.

Conn. Agencies Regs. § 16a-32-6

Effective March 6, 1980; Amended March 8, 2007; Transferred from § 16a-24b-8, October 2, 2007