Any statute enacted prior to or on August 9, 2006 changing the name of the Division of Reclamation, Mining and Safety to the Division of Reclamation, Mining and Safety, shall not impair the legal status or effect of any and all permits, permit obligations, financial warranties, performance warranties, contracts, property rights and/or any other obligations or legal relationships that were entered into between any entity or individual and the Division of Reclamation, Mining and Safety prior to the name change. All such obligations will remain legally binding and shall not be impaired by any such name change. Any statute enacted after August 9, 2006 changing the name of the Division of Reclamation, Mining and Safety to any other name, shall not impair the legal status or effect of any and all permits, permit obligations, financial warranties, performance warranties, contracts, property rights and/or any other obligations or legal relationships that were entered into between an entity or individual and the Division of Reclamation, Mining and Safety prior to such name change. All such obligations will remain legally binding and shall not be impaired by any such name change.
STATEMENTS OF BASIS AND PURPOSE
These modifications to the Rules are made pursuant to the authority granted to the Mined Land Reclamation Board in Sections 34-32-104, 34-32-105(3), 34-32-106(1)(b), and 34-32-108(1) C.R.S.
The specific authority for these rules is provided in Section 34-32-108(1), C.R.S.-- "The Board may adopt and promulgate reasonable rules and regulations respecting the administration of this article and article 32.5 of this title and in conformity therewith."
The primary purpose of the amendments include the deletion of the custom milling definition and exemption, clarifying and amending certain portions of the existing rules including the size of the required posted sign, an estimated completion date for Notices of Intent to Conduct Prospecting Activities, and general editorial clean up.
Regulatory Additions and Amendments:
Deleted Rule 1.1 Definition- Custom Mill is a mill that is not engaged in the processing of ore from any permitted mine that is owned or under common control with the milling facility or the entity operating the milling facility. An Applicant or Operator who intends to mill ores from other mining operations must submit adequate information to demonstrate that waste (material or stream) from such ores will be processed or disposed of in a manner to protect human health, property and the environment. "Custom Mill" does not include mills regulated by the Radiation Control Division of the Colorado Department of Public Health and the Environment under Part 18 of Rules and Regulations Pertaining to Radiation Control.
Deleted Rule 1.2.1 reclamation Permit Exemption Specified by Rule- The Board has determined that certain types of activities do not need reclamation permits either because the excavated substance is not a mineral as defined in Section 34-32-103(7), Colorado Revised Statutes 1984, as amended or because the activity is not a mining operation as defined by Section 34-32-103(8), C.R.S. 1984, as amended. Such activities include the following: (e) a custom mill.
The statutory definition of "Mining Operation" in the Colorado Mined Land Reclamation Act ("Act") includes the following operations on affected lands: Transportation; concentrating; milling; evaporation; and other processing. § 34-32-103(8), C.R.S. "Custom Mill" is not defined or even mentioned in the Act.
After several discussions with the Colorado Department of Public Health and the Environment, Hazardous Materials and Waste Management Division (HMWMD), the Division of Reclamation Mining and Safety ("Division") determined that the regulatory definition of Custom Mill was causing unnecessary confusion over jurisdiction and authority and that CDPHE was not actively regulating "custom mills."
An updated and revised Memorandum of Understanding ("MOU") between HMWMD and the Division was executed in June of 2017. The revised MOU states:
Stakeholder Involvement in the Process
The following describes the Division's effort to work with and reach out to stakeholders:
The Division utilized various methods to inform individual industry representatives, industry trade associations, environmental organizations, federal government agencies, and the general public of the proposed regulatory revisions and rule-making process. These methods included:
The Mined Land Reclamation Board adopted amendments based on stakeholder input and testimony at the scheduled rule-making hearing on May 22, 2019.
2 CCR 407-1-9