Each Submission for a Permit (or component thereof) is subject to a deadline by which the DEC must make a decision i.e., take a final vote. Listed are the applicable time periods, measured from the date of the DOC. The time limits for Level One reviews may be extended by mutual written agreement of the Applicant and the Director. The time limits for Level Two reviews also may be extended by a written agreement of the Applicant and the DEC. In a Submission with more than one component, the longest time limit associated with one component shall apply to the entire Submission.
TABLE 3: TIME LIMITS FOR REVIEW
Time Limit in Days | |
Level One Review | |
Lotting Plan | 14 |
Development Plan | 21 |
Engineering Adjustment | 14 |
Building or Occupancy Permit | 30 |
Other reviews authorized in the By-laws, Article III, Section D | 21 |
Level Two Review | (inclusive of the date of the DEC's vote) |
Site Plan Review | 75 |
Subdivision Approval | 75 |
Wetlands | 63 |
Variances | 90 |
Reconsiderations (measured from the date of the request) | 45 |
Historic District Certificates of Appropriateness | 45 |
974 CMR, § 1.08