Additional limitations and conditions may apply, including but not limited to, 40 CFR Part 63, Subpart ZZZZ; 40 CFR Part 60, Subpart IIII; and 40 CFR Part 60, Subpart JJJJ.
The total facility, including the new or modified paint spray booth, shall use less than 670 gallons per calendar month of all materials containing VOCs, or alternatively, has an emission rate of less than 2.5 tons of VOC per calendar month. This emission rate includes all coating operations at the facility. The owner/operator is subject to the reporting requirements of 310 CMR 7.12.
310 CMR 7.18(3) Metal Furniture Surface Coating;
310 CMR 7.18(4) Metal Can Surface Coating;
310 CMR 7.18(5) Large Appliance Surface Coating;
310 CMR 7.18(6) Magnetic Wire Insulation Surface Coating;
310 CMR 7.18(10) Metal Coil Coating;
310 CMR 7.18(11) Surface Coating of Miscellaneous Metal Parts and Products;
310 CMR 7.18(21) Plastic Parts Surface Coating;
310 CMR 7.18(22) Leather Surface Coating;
310 CMR 7.18(23) Wood Products Surface Coating;
310 CMR 7.18(24) Flat Wood Paneling Surface Coating; and
310 CMR 7.18(28) Automotive Refinishing.
Operations not listed in 310 CMR 7.03(16)(b) are not covered by this exemption and require either a Limited Plans Application (LPA) or Comprehensive Plans Application (CPA) as required by 310 CMR 7.02.
The total facility including, but not limited to, the new or modified printing press, and non-printing operations at the facility, shall use less than 670 gallons per calendar month of all materials containing VOCs or, alternatively, the total facility emission rate shall be less than 2.5 tons of VOC per calendar month. The owner/operator is subject to the reporting requirements of 310 CMR 7.12; or
The Department may grant an extension to operate the temporary boiler beyond 120 days. Such an extension shall be considered upon receiving a written request for an extension. Approval of an extension will be issued in writing.
310 CMR, § 7.03