220 CMR, § 101.04

Current through Register 1536, December 6, 2024
Section 101.04 - Notice of Proposed Construction
(1) Notice of proposed construction shall be filed with the Department at least 14 days prior to the start of any of the following projects:
(a) All new and replacement pipeline installation projects of 1,000 feet or more in length.
(b) All new and replacement pipeline installation projects where the pipeline will have an MAOP of 125 psig or more.
(c) All Uprating projects.
(2) If there are no construction projects in a calendar year meeting the requirements of 220 CMR 101.04(1), then an operator shall file with the Department a notice of proposed construction at least 14 days prior to the start of any project for no fewer than three projects, provided that at least three projects are undertaken.

220 CMR, § 101.04

Amended by Mass Register Issue 1334, eff. 3/10/2017.
Amended by Mass Register Issue 1432, eff. 12/11/2020.
Amended by Mass Register Issue 1532, eff. 10/11/2024.