105 CMR, § 120.635

Current through Register 1537, December 20, 2024
Section 120.635 - Commencement of Construction

Commencement of construction of a new irradiator may not occur prior to the submission to the Agency of both an application for a license for the irradiator and the prescribed fee. As used in 105 CMR 120.620 through 120.693, the terms "commencement of construction" and "construction" are defined in 105 CMR 120.102. Any activities undertaken prior to the issuance of a license are entirely at the risk of the applicant and have no bearing on the issuance of a license with respect to the requirements of M.G.L. c. 111, §§ 3, 5M, 5N, 5O, and 5P, rules, regulations, and orders issued under M.G.L. c. 111, §§ 3, 5M, 5N, 5O, and 5P.

105 CMR, § 120.635

Amended by Mass Register Issue 1307, eff. 2/26/2016.