Section 734.002-70 - USAID policy

In order for an USAID acquisition to be considered a major system acquisition it must meet the criteria of OMB Circular A-109 and FAR part 34, and must have an estimated value of $15 million or more during the first year of the contract. All major systems acquisition must be approved in advance by the M/OAA Director.