46 C.F.R. § 143.245

Current through October 31, 2024
Section 143.245 - Readiness and testing
(a) Essential systems or equipment must be regularly tested and examined. Tests and examinations must verify that the system or equipment functions as designed. If a component is found unsatisfactory, it must be repaired or replaced. Test and examination procedures must be in accordance with manufacturer's instructions or the Towing Safety Management System (TSMS) applicable to the vessel, if the vessel has a TSMS.
(b) Each towing vessel must perform the applicable tests in Table 143.245(b) of this section. The tests required by this section must be recorded in accordance with part 140 of this subchapter.

Table 143.245(b)-Required Tests and Frequency

Tests of: Frequency:
Propulsion controls; ahead and astern at the operating stationBefore the vessel gets underway, but no more than once in any 24 hour period.
Steering controls at the operating stationBefore the vessel gets underway, but no more than once in any 24 hour period.
Pilothouse alerter systemWeekly.
All alternate steering and propulsion controlsAt least once every 3 months.
Power supply for alarm actuation circuits for alarms required by § 143.230 At least once every 3 months.
Communications required by § 143.240 Weekly.
General alarm if the vessel is so equippedWeekly.
Emergency lighting and power if the vessel is so equippedAt least once every 3 months.
Charge of storage batteries if the vessel is so equipped, for emergency lighting and powerAt least once every 3 months.
Alarm setpointsTwice every 5 years, with no more than 3 years elapsing since last test.
Pressure vessel relief valvesTwice every 5 years, with no more than 3 years elapsing since last test.
All other essential systemsAt least once every 3 months.

46 C.F.R. §143.245

81 FR 40101 7/20/2016