Section 250.751 - Coiled tubing testing requirements

You must test the coiled tubing unit in accordance with § 250.737(a), (b), (c), (d)(9), and (d)(10) . You must successfully pressure test the dual check valves to the rated working pressure of the connector, the rated working pressure of the dual check valve, expected surface pressure, or the collapse pressure of the coiled tubing, whichever is less. The test interval for coiled tubing operations must include a 10 minute high-pressure test for the coiled tubing string.

30 C.F.R. §250.751

84 FR 21984 , May 15, 2019
84 FR 21984 , 7/15/2019