Cal. Code Regs. tit. 20 § 2026

Current through Register 2024 Notice Reg. No. 50, December 13, 2024
Section 2026 - Agency Comments
(a) Within 60 days after the acceptance of an application under this Article, the California Independent System Operator or other interconnecting authority and all local, regional, and state agencies that have jurisdiction over the project or would have jurisdiction, but for the exclusive jurisdiction of the commission, shall file and serve on all parties their preliminary approval, comments, determinations, and opinions.
(b) Within 100 days after the acceptance of an application, all local, regional, and state agencies that have jurisdiction over the project or would have jurisdiction, but for the exclusive jurisdiction of the commission, shall file and serve on all parties their final comments, determinations, and opinions.

Cal. Code Regs. Tit. 20, § 2026

1. New section filed 11-27-2000 as an emergency; operative 11-27-2000 (Register 2000, No. 48). A Certificate of Compliance must be transmitted to OAL by 3-27-2001 or emergency language will be repealed by operation of law on the following day.
2. Certificate of Compliance as to 11-27-2000 order transmitted to OAL 3-21-2001 and filed 4-25-2001 (Register 2001, No. 17).

Note: Authority cited: Sections 25213 and 25218(e), Public Resources Code. Reference: Sections 25519(f), 25519(j), 25523(d) and 25550, Public Resources Code.