Cal. Code Regs. tit. 14 § 1777.2

Current through Register 2024 Notice Reg. No. 49, December 6, 2024
Section 1777.2 - Production Facility Reporting Requirements
(a) Any operator acquiring the right to operate a facility shall notify the local district office in writing within 30 days after finalizing the sale or transfer with the following information:
(1) The facility location;
(2) A unique alphanumeric tank identification number designated by the operator consisting of 10 characters or less;
(3) The date the transaction became effective; and
(4) The facility lease name.
(b) Operators shall notify the local district office within 60 days after completing new construction, alteration, or decommissioning of a production facility, or reactivating an Out-of-Service tank . This notification report shall describe the activities and reference the production facilities that have been added, altered or decommissioned.
(c) Operators shall notify the local district office two days or more prior to conducting required tank or pipeline testing specified in Sections 1773.4 or 1774.1.

Cal. Code Regs. Tit. 14, § 1777.2

1. New section filed 12-30-2010; operative 1-29-2011 (Register 2010, No. 53).

Note: Authority cited: Sections 3013 and 3270, Public Resources Code. Reference: Sections 3106, 3202 and 3270, Public Resources Code.