Current through Register Vol. 30, No. 45, November 8, 2024
Section R9-34-303 - Computation of TimeA. Computation of time in calendar days begins the day after the act, event, or decision and includes all calendar days and the final day of the period. If the final day of the period is a weekend or legal holiday, the period is extended until the end of the next day that is not a weekend or a legal holiday.B. Computation of time for working day begins the day after the act, event, or decision and includes all working days. Ariz. Admin. Code § R9-34-303
New Section made by final rulemaking at 10 A.A.R. 828, effective April 3, 2004 (Supp. 04-1).