where:
C p = the total projected cost of fuel and purchased power for the future period;
B = the balance in the cost-of-power balancing account;
S p = the projected kilowatt-hour sales for the future period; and
C b = the base cost of power.
3 AAC 52.503
Authority:AS 42.05.141
AS 42.05.151
AS 42.05.381
AS 42.45.110
AS 42.45.130
AS 42.45.160
AS 42.45.170