A utility may not calculate demand charge billings for any self-generating customer based upon that customer's demand as measured during forced outages of customer generation facilities required to resynchronize and return the customer's self-generation output to parallel operation with the utility during the one-hour period after power to the self-generating customer is restored following a utility system outage that originates on the utility's side of its metering to the customer affecting service to the self-generating customer.
3 AAC 52.462
Authority:AS 42.05.141
AS 42.05.381
AS 42.05.391