From Casetext: Smarter Legal Research

White v. 855 MRU LLC

Supreme Court, Kings County
Feb 14, 2019
2019 N.Y. Slip Op. 29037 (N.Y. Sup. Ct. 2019)

Opinion

508860/14

02-14-2019

Wayne WHITE and Sharice White, Plaintiff, v. 855 MRU LLC, Durst Fetner Residential LLC, and Gotham Construction Company, LLC, Defendants.

ROPERS MAJESKI KOHN & BENTLEY, For Def. by Douglas Miller, 750 Third Avenue, 25th Floor, NY, NY 10017 646.454.3247, SACKS AND SACKS, LLP, For Plaintiff, 150 Broadway, 4th floor, NY, NY 10038, By Edward W. Ford


ROPERS MAJESKI KOHN & BENTLEY, For Def. by Douglas Miller, 750 Third Avenue, 25th Floor, NY, NY 10017

646.454.3247, SACKS AND SACKS, LLP, For Plaintiff, 150 Broadway, 4th floor, NY, NY 10038, By Edward W. Ford

Johnny L. Baynes, J.

Plaintiffs, Wayne and Sharice White, in this personal injury action brought pursuant to Labor Law § 240 (1) (the "Scaffold Law") and Labor Law § 241(6), move by August 7, 2018 notice of motion for a CPLR § 3212 Order granting summary judgment and setting the matter down for an "inquest" to assess damages. Defendants 855 MRU LLC and Gotham Construction Company LLC ("Gotham") cross-moved on that same day for summary judgment pursuant to CPLR § 3212 finding that Plaintiffs cannot establish liability, and dismissing the action. Plaintiffs and Defendants respectively submitted December 13, 2018 and December 11, 2018 affirmations in opposition to each other's motions, both mislabeled as an affirmations "in reply." Neither party submitted actual reply affirmations or affidavits.

After issue was joined and discovery completed, the material undisputed facts are as follows. During the Summer of 2014, Plaintiff, Wayne White ("White") was a union lather employed by non-party, Cross County Construction LLC ("Cross-Country"), which had its own general foreman and deputy foreman on the underlying accident site. White does not recall the accident itself, but his basic understanding was that a wooden beam fell from the top floor directly above him into the area where he was working, somehow striking him. Significantly, White testified that the only workers working in the area above him were fellow Cross-Country employees.

As to the relationship between the named defendants, 855 MRU owned the underlying property at the time of the accident. White testified that only his employer, Cross Country, directed his work or controlled the area of work site, however, Gotham was Cross Country's "construction manager," and was generally responsible for coordinating of all trades pertaining to the construction.

Contrary to Defendants' claim that no witness had personal knowledge of exactly how the underlying accident occurred, White's witness, Marouisse Wren ("Wren"), testified that he witnessed the accident first hand. Wren's unrefuted testimony is that at about 8:45 a.m. on the date in question, he was working on the same floor as White when "one of the carpenters working above them was cutting wood and the piece he was cutting fell through a hole in the floor above them and fell approximately seven feet and hit [White] in the head."

Wren further testified, and it is unrefuted, that there was no netting or any other protective devices to prevent any objects from falling onto the floor where White and he were working at the time of the accident, and Gotham's "safety manager," Richard Agresta ("Agresta"), acknowledged that "either Cross Country or Gotham or both would need to have some sort of procedure or protocol which would keep a worker below safe."

* * *

In analyzing the two competing summary judgment motions, it is initially noted that Section 240(1) of the Labor Law provides:

"All contractors and owners and their agents ... in the erection, demolition, repairing, altering, painting, cleaning or pointing of a building or structure shall furnish or erect, or cause to be furnished or erected for the performance of such labor, scaffolding, hoists, stays, ladders, slings, hangers, blocks, pulleys, braces, irons, ropes, and other devices which shall be so constructed, placed and operated as to give proper protection to a person so employed."

Section 241(6) of the Labor Law similarly requires that all contractors and owners and their agents, comply with the requirement that all work areas "be so constructed, shored, equipped, guarded, arranged, operated and conducted as to provide reasonable and adequate protection and safety to the persons employed therein or lawfully frequenting such places."

It is well settled that the liability of an owner, or a general contractor, is absolute upon proof that a worker's injuries were proximately caused by violation of their obligations under the Scaffold Law. See , e.g. , Haimes v. New York Tel. Co. , 46 N.Y.2d 132, 412 N.Y.S.2d 863, 385 N.E.2d 601 (1978) ; Silvers v. E.W. Howell, Inc. , 129 A.D.2d 694, 514 N.Y.S.2d 455 (2nd Dept. 1987) ; Santos v. Sure Iron Works , 166 A.D.2d 571, 560 N.Y.S.2d 857 (2nd Dept. 1990).

Moreover, in Ross v. Curtis-Palmer Hydro-Electric Company , 81 N.Y.2d 494, 601 N.Y.S.2d 49, 618 N.E.2d 82 (1993), the Court of Appeals further noted that the Scaffold Law duties are nondelegable, and that an owner or contractor who breaches that duty may be held liable regardless of whether it actually exercised supervision or control over the work. See , e.g. , Haimes v. New York Tel. Co. , 46 N.Y.2d 132, 136-137, 412 N.Y.S.2d 863, 385 N.E.2d 601 ). The Court further opined that the Scaffold Law " ‘is to be construed as liberally as may be for the accomplishment of the purpose for which it was ... framed’ " Koenig v. Patrick Constr. Corp. , 298 N.Y. 313, 319, 83 N.E.2d 133 (1948).

In the landmark decision, De Haen v. Rockwood Sprinkler Co. , 258 N.Y. 350, 179 N.E. 764 (1932), in an opinion by Chief Judge Cardozo, the Court of Appeals recognized that a hazard arising from violation of a statute would not, in and of itself, establish liability if the plaintiff's injury was the result of a "hazard of a different kind," however, the Court allowed that plaintiff to recover for the death of her decedent, who was killed by a radiator that fell into an unprotected hoistway, even though the applicable statute, former Labor Law § 241(5), was designed to protect workers from the hazard of falling into a shaftway. Judge Cardozo wrote for the majority that recovery should be allowed where the injury sustained was not specifically covered but was nonetheless within the statute's "zone of apprehension."

In understanding the foregoing "zone of apprehension" with respect to the Scaffold Law, the Court of Appeals more recently clarified in Rocovich v. Consolidated Edison Co. , 78 N.Y.2d 509, 577 N.Y.S.2d 219, 583 N.E.2d 932 (1991), that the Scaffold Law is only aimed at "elevation-related" hazards and that injuries resulting from other types of hazards are not compensable under that statute, even if proximately caused by the absence of adequate scaffolds or other required safety devices. Thus, in Rocovich , the Court concluded that, although that plaintiff's injury was proximately caused by a "slip and fall" on an oil-covered area, and was severe, it was not the kind of harm typically associated with elevation-related hazards, despite the injury being "related to the effects of gravity." The Rocovich Court further opined that the Scaffold Law evinces a clear legislative intent to provide "exceptional protection" for workers against the "special hazards" that arise when the work site either is itself elevated or is positioned below the level where "materials or load [are] hoisted or secured, and that the "special hazards" referred to therein do not encompass any and all perils that may be connected in some tangential way with the effects of gravity, but rather is limited to such specific gravity-related accidents as falling from a height or being struck by a falling object that was improperly hoisted or inadequately secured.

In Fabrizi v. 1095 Avenue of the Americas, LLC , 22 N.Y.3d 658, 985 N.Y.S.2d 416, 8 N.E.3d 791 (2014), the Court of Appeals further clarified that in order for a plaintiff to prevail on summary judgment in a section 240(1)"falling object" case, the injured worker must demonstrate both the existence of a hazard contemplated under that statute, and that at the time the object fell, it either was being "hoisted or secured," or "required securing for the purposes of the undertaking."

In the case at hand, while Defendants alleged that neither Cross Country nor the NYC Department of Buildings were able to confirm where the piece of wood that struck Plaintiff came from or exactly how the accident occurred, in reality, Plaintiff's unrefuted witness established that the injury was proximately caused by a piece of wood falling from Cross Country's overhead carpentry work area.

Accordingly, it is this Court's opinion that Plaintiffs have established that ongoing carpentry work involving loose lumber pieces that are foreseeably heavy enough to cause serious injury if the fell on workers below constitutes a special hazard anticipated by the Scaffold Law, and that where as here a falling piece proximately caused plaintiff's injury, the plaintiff has established a prima facie, albeit rebuttable presumption of the defendants' non-delegable liability for such "falling objects" under the Scaffold Law, as opposed to an "inadequate safety design" scenario which would require a different analysis, and that such prima facie showing renders Defendants arguments as to whether or not such lumber was being "hoisted" at the time that it fell, and shifts the burden of proof to Defendants to offer factual evidence rebutting such prima facie rebuttable presumption. Estate of Zimmerman v. Mitsubishi Motors Credit of America, Inc. , 34 A.D.3d 628, 824 N.Y.S.2d 667 (2nd Dept. 2006). This Court finds that Defendants failed to adequately rebutt the foregoing presumption, and Defendants' liability under the Scaffold Law is established as a matter of law. See Outar v. City of New York , 5 N.Y.3d 731, 799 N.Y.S.2d 770, 832 N.E.2d 1186 (2005) ; Santos v. Sure Iron Works , 166 A.D.2d 571, 560 N.Y.S.2d 857 (2nd Dept. 1990) ; Humphrey v. Park View Fifth Ave. Associates, LLC , 113 A.D.3d 558, 979 N.Y.S.2d 317 (1st Dept. 2014) Mercado v. Caithness Long Island LLC , 104 A.D.3d 576, 961 N.Y.S.2d 424 (1st Dept. 2013).

To the extent that Defendants argue that the First Department cases cited by Plaintiff are "inconsistent" with the Court of Appeals and Appellate Division Second Department, and that such First Department cases are "nonbinding" within the Second Department, it is Defendants' foregoing arguments that are misguided. First, this Court is not at liberty to disregard higher Courts' precedents, merely because they are from different Departments, unless such precedents directly conflict with precedents from this Department. More importantly, however, Defendants have not revealed any such incongruity among the cases cited, and have merely failed to reconcile them.

Thus, for example, in Millette v. Tishman Const. Corp. , 144 A.D.3d 1113, 42 N.Y.S.3d 285 (2d Dept. 2016), relied upon heavily by Defendants, the plaintiff therein relied upon an unsworn statement by the plaintiff's coworker that the falling plywood therein, when a worker accidentally stepped on a piece of plywood, that was being used, without hoists, to "frame a wall," where the plywood piece was located "beyond it[s] normal designated spot ...." The Millette Court found that such unsworn statement failed to demonstrate that the falling plywood was required to be secured for purposes of the undertaking, namely "framing a wall," and concluded that such unsworn statement was insufficient to establish the plaintiff's entitlement to judgment as a matter of law. The Millette Court was further guided by that plaintiff's own supervisor's sworn affidavit admitting that the area where he was working was not normally exposed to falling material or objects.

Moreover, Defendants' reliance upon the Fabrizi case further demonstrates Defendants' failure to distinguish between such "falling objects" cases and "inadequate device" cases. The Fabrizi case was not a falling objects case, as presented here, but rather an "inadequate device" case in which the Court of Appeals found that a device therein, which was not created for the purpose of preventing falling objects, was not covered by the statute in the event of a purely isolated, random object that happened to fall. That analysis is different from those cases analyzing ongoing risks of falling objects where, as here, no safety device is present, but one should have been present.

Thus, where, as here, in a falling objects case, Plaintiffs rely upon sworn affidavits, rather than unsworn statements, and such sworn affidavits attest to ongoing overhead carpentry work involving heavy lumber, and the absence of any safety device, and falling lumber does in fact fall and proximately injure a worker below, there is a rebuttable presumption that such lumber should be secured to avoid such injury workers below. Here, Defendants have not submitted an affidavit or evidence rebutting that presumption, for example, attesting that such carpentry work was for a singular quick repair, that such work was being done in an abnormal location, or that the plaintiff was working in an area not normally exposed to falling material or objects.

Defendants did submit evidence that it was Cross Country's policy to secure lumber for storage consistent with Section 23-2.1(a)(1) of the NY Industrial Code, but not while such lumber was in use, however, that point would appear to go more to the issue of comparative or contributory negligence, as opposed to the issue of Defendants' non-delegable obligations under the Scaffold Law. No factual findings or legal rulings are made with respect to any issues involving comparative negligence of any parties, or non-parties.

Finally, Defendants' reliance upon a case involving a hammer that accidentally slipped out of worker's hand as opposed to ongoing overhead heavy lumber carpentry work is no more analogous to the current case, and punctuates Defendants' failure to at least assume the possibility that the cases may be distinguishable, rather than inconsistent.

WHEREFORE, it is hereby

ORDERED AND ADJUDGED that Defendants' motion for summary judgment is granted solely to the extent of dismissing Plaintiff's claims as to Defendant, Durst Fetner, in view of Defendants' unrefuted affidavit that such entity has no relationship to the construction site at issue; and it is further

ORDERED AND ADJUDGED that Defendants' said motion is denied in all other respects; and it is further

ORDERED AND ADJUDGED that Plaintiff's motion for summary judgment is granted, solely to the extent of finding that Plaintiff has established the remaining Defendants' non-delegable liability pursuant to Labor Law §§ 240(1) and 241(6). Plaintiff may apply, on notice, for a "trial" date, as opposed to the requested "inquest," on the issue of damages, after first scheduling a pre-trial conference with respect to any anticipated motions in limine .

The foregoing constitutes the Decision and Order of the Court.


Summaries of

White v. 855 MRU LLC

Supreme Court, Kings County
Feb 14, 2019
2019 N.Y. Slip Op. 29037 (N.Y. Sup. Ct. 2019)
Case details for

White v. 855 MRU LLC

Case Details

Full title:Wayne White and Sharice White, Plaintiff, v. 855 MRU LLC, Durst Fetner…

Court:Supreme Court, Kings County

Date published: Feb 14, 2019

Citations

2019 N.Y. Slip Op. 29037 (N.Y. Sup. Ct. 2019)
2019 N.Y. Slip Op. 29037