Opinion
September 21, 2010.
Contracts — Quantum Meruit — Pattern of Conduct and Performance as Binding Construction Contract.
September 21, 2010.
Contracts — Quantum Meruit — Pattern of Conduct and Performance as Binding Construction Contract.
Full title:Skanska USA Bldg. Inc. v. Long Is. Univ
Court:Appellate Term of the Supreme Court of New York, First Department
Date published: Sep 21, 2010
The first cause of action in the complaint, which seek to foreclose a mechanic's lien, is equitable in nature…