Robert NORERO, appellant, v. 99–105 THIRD AVENUE REALTY, LLC, et al., respondents, et al., defendant (and a third-party action).

Larry Dorman, P.C., Astoria, N.Y. (Michael S. Murphy of counsel), for appellant. Tompkins, McGuire, Wachenfeld & Barry, LLP, New York, N.Y. (William C. Kelly of counsel), for respondents.



Larry Dorman, P.C., Astoria, N.Y. (Michael S. Murphy of counsel), for appellant. Tompkins, McGuire, Wachenfeld & Barry, LLP, New York, N.Y. (William C. Kelly of counsel), for respondents.
PETER B. SKELOS, J.P., ANITA R. FLORIO, SHERI S. ROMAN, and ROBERT J. MILLER, JJ.

In an action to recover damages for personal injuries, the plaintiff appeals, as limited by his brief, from so much of an order of the Supreme Court, Queens County (Lane, J.), dated April 18, 2011, as denied, as premature, his motion, in effect, for summary judgment on the issue of liability on the causes of action alleging violations of Labor Law §§ 240(1) and 241(6) insofar as asserted against the defendants 99–105 Third Avenue Realty, LLC, and Bella Builders Associates, LLC.

ORDERED that the order is reversed insofar as appealed from, on the law, with costs, and the plaintiff's motion, in effect, for summary judgment on the issue of liability on the causes of action alleging violations of Labor Law §§ 240(1) and 241(6) insofar as asserted against the defendants 99–105 Third Avenue Realty, LLC, and Bella Builders Associates, LLC, is granted.

The defendant 99–105 Third Avenue Realty, LLC (hereinafter 99–105), which owned a multi-story building, engaged the defendant Bella Builders Associates, LLC (hereinafter Bella), as general contractor on a construction project at the building. Pursuant to subcontracts with Bella, the defendant Casur Corp. performed the “interior core and shell work,” and the third-party defendant, JLC Corp. (hereinafter JLC), performed asbestos removal work.

On July 26, 2008, the plaintiff, an employee of JLC, allegedly was injured when, while working on the fifth floor of the building, he partially fell into an unprotected opening in the floor that was large enough for his body to have passed through. He commenced this action, alleging, inter alia, violations of Labor Law §§ 240(1) and 241(6).

The plaintiff moved, in effect, for summary judgment on the issue of liability on his causes of action alleging violations of Labor Law §§ 240(1) and 241(6) insofar as asserted against 99–105 and Bella. However, the Supreme Court, observing that certain discovery remained outstanding, denied that motion as premature.

“Labor Law § 240(1) imposes upon owners and general contractors, and their agents, a nondelegable duty to provide safety devices necessary to protect workers from risks inherent in elevated work sites” ( McCarthy v. Turner Constr., Inc., 17 N.Y.3d 369, 374, 929 N.Y.S.2d 556, 953 N.E.2d 794;see Valensisi v. Greens at Half Hollow, LLC, 33 A.D.3d 693, 695, 823 N.Y.S.2d 416). To prevail on a cause of action alleging a violation of Labor Law § 240(1), a plaintiff must establish that the statute was violated and that the violation was a proximate cause of his or her injuries ( see Blake v. Neighborhood Hous. Servs. of N.Y. City, 1 N.Y.3d 280, 287–289, 771 N.Y.S.2d 484, 803 N.E.2d 757).

Labor Law § 241(6) imposes upon owners and general contractors, and their agents, a nondelegable duty to provide reasonable and adequate protection and safety for workers, and to comply with the specific safety rules and regulations promulgated by the Commissioner of the Department of Labor ( see Comes v. New York State Elec. & Gas Corp., 82 N.Y.2d 876, 878, 609 N.Y.S.2d 168, 631 N.E.2d 110;Ross v. Curtis–Palmer Hydro–Elec. Co., 81 N.Y.2d 494, 501–502, 601 N.Y.S.2d 49, 618 N.E.2d 82;Russin v. Louis N. Picciano & Son, 54 N.Y.2d 311, 317–318, 445 N.Y.S.2d 127, 429 N.E.2d 805). To prevail on a cause of action alleging a violation of Labor Law § 241(6), a plaintiff must establish the violation of an Industrial Code provision that sets forth specific, applicable safety standards ( see Ross v. Curtis–Palmer Hydro–Elec. Co., 81 N.Y.2d at 503–505, 601 N.Y.S.2d 49, 618 N.E.2d 82).

Here, the plaintiff established, prima facie, that he was not provided with proper protection under Labor Law § 240(1), that the failure to provide such protection also violated a specific and applicable provision of the Industrial Code ( see12 NYCRR 23–1.7[b][1][i] ), and that this failure was the proximate cause of his alleged injuries ( see Ortiz v. 164 Atl. Ave., LLC, 77 A.D.3d 807, 808–810, 909 N.Y.S.2d 745). In opposition, 99–105 and Bella failed to raise a triable issue of fact. Furthermore, contrary to their contention, the plaintiff's motion was not premature, as they failed to demonstrate how discovery may reveal or lead to relevant evidence or that “facts essential to opposing the motion were exclusively within” another party's “knowledge and control” ( Espada v. City of New York, 74 A.D.3d 1276, 1277, 903 N.Y.S.2d 237;seeCPLR 3212[f]; Naranjo v. Star Corrugated Box Co., Inc., 22 A.D.3d 545, 545–546, 802 N.Y.S.2d 507).

Accordingly, the Supreme Court should have granted the plaintiff's motion, in effect, for summary judgment on the issue of liability on the causes of action alleging violations of Labor Law §§ 240(1) and 241(6) insofar as asserted against 99–105 and Bella.


Summaries of

Norero v. 99-105 Third Avenue Realty, LLC

Supreme Court, Appellate Division, Second Department, New York.
Jun 6, 2012
96 A.D.3d 727 (N.Y. App. Div. 2012)
Case details for

Norero v. 99-105 Third Avenue Realty, LLC

Case Details

Full title:Robert NORERO, appellant, v. 99–105 THIRD AVENUE REALTY, LLC, et al.…

Court:Supreme Court, Appellate Division, Second Department, New York.

Date published: Jun 6, 2012

Citations

96 A.D.3d 727 (N.Y. App. Div. 2012)
945 N.Y.S.2d 720
2012 N.Y. Slip Op. 4325

Citing Cases

Ramos v. Lynch

Similarly, Salt has failed to establish prima facie entitlement to summary judgment dismissing plaintiffs…

Seales v. Trident Structural Corp.

However, the defendants failed to establish their prima facie entitlement to judgment as a matter of law…