From Casetext: Smarter Legal Research

E.C.I. Corp. v. G.G.C. Co.

Supreme Court of Minnesota
Jan 2, 1976
306 Minn. 433 (Minn. 1976)

Summary

involving issue of whether appeal began to run from the original order or as amended, corrected order

Summary of this case from In the Matter of the Welfare of J.R

Opinion

No. 45356.

January 2, 1976.

Appeal and error — appeal from amended judgment — timeliness — issues which could have been raised on appeal from original judgment.

1. Rule 104.01, Rules of Civil Appellate Procedure, which allows 90 days to take an appeal from a judgment, applies to each issue that could be raised by appeal from the judgment. Ordinarily a modification of judgment does not extend the time to appeal issues that could have been raised in an appeal from the first judgment, but under the circumstances of this case the appeal was allowed even though brought more than 90 days following the first judgment.

Mechanics liens — action for work done on uncompleted project — amount of lien.

2. In an action under the mechanics lien statute, when the project in dispute has not been completed, Minn. St. 514.03 contemplates that the lien shall be measured according to ordinary common-law principles.

Action in the Dakota County District Court to foreclose a mechanics lien for labor and materials allegedly furnished by plaintiff to landscape a building under construction. After findings for plaintiff, C. A. Rolloff, Judge, defendant G.G.C. Co. appealed from the judgment entered. Affirmed.

Cox, King Stern and Leo G. Stern, for appellant.

Byron W. McCullagh, for respondent.

Heard before Peterson, Kelly, and MacLaughlin, JJ., and considered and decided by the court en banc.


Defendant G.G.C. Co. appeals from a judgment entered in favor of plaintiff E.C.I. Corporation pursuant to the mechanics lien statute, Minn. St. 514.03. Plaintiff, a landscaping company, in August 1971 contracted with defendant, owner of an apartment complex under construction, to supply plantings, sod, and gravel walks for the complex for an agreed price of $55,000. Problems arose, each party became dissatisfied, and finally before the project was substantially completed all work and payments ceased. Plaintiff sued in the district court of Dakota County under the mechanics lien statute, and the court awarded judgment based on the reasonable value of what plaintiff had provided. Defendant appeals from the judgment. We affirm.

1. Plaintiff asserts initially that defendant's appeal is untimely. The chronology on which plaintiff rests its assertion is as follows: On April 2, 1974, the district court filed the original findings, conclusions, and order for judgment. On May 3, 1974, the clerk of court made a judgment entry which mentioned and conformed to the first order for judgment. Then on June 17, 1974, the clerk made a second judgment entry correcting the mistake in the first and mentioning the amended order for judgment which was filed April 16, 1974. Defendant filed its notice of appeal September 5, 1974. Rule 104.01, Rules of Civil Appellate Procedure, provides that an appeal from a judgment may be taken within 90 days after the entry thereof. This appeal is timely if computed from the entry of the amended judgment, but is not timely if time is computed from the original entry.

Limitations on time to appeal are designed to expedite the final resolution of litigation, with due consideration to fairness and certainty of procedure. Rule 104.01 contemplates that every litigant shall have 90 days, and only 90 days, to take an appeal from a judgment. The 90-day period for appealing any issue raised by a judgment begins at the time that issue first becomes appealable, and once the time begins to run it ordinarily will not be extended.

The disputed application of the rule in this case arises because of a modification of a judgment. We held in Malmgren v. Phinney, 65 Minn. 25, 67 N.W. 649 (1896), that once the time to appeal an issue has expired, it may not later be appealed because of a modification of judgment except that new issues arising from the modification are appealable. Dicta in Billson v. Lardner, 67 Minn. 35, 69 N.W. 477 (1896), at the following term of court, however, suggests an arguable deviation from that holding, although it makes no mention of Malmgren. The correct application of Rule 104.01 is that the time to appeal an issue begins to run anew from a modification of judgment when the issue was for some reason not appealable before the modification.

Other jurisdictions have varied in their application of limitations on time to appeal in cases of modified judgments, as indicated by the annotation at 21 A.L.R. 2d 285.

The rules of this court are designed to effectuate the orderly administration of justice and do not control its jurisdiction, for it retains the constitutional power to hear and determine, as a matter of discretion, any appeal in the interest of justice. A strict application of the rule would bar the appeal in this case, for it appears that the defendant could have raised all its substantive issues on an appeal from the first judgment. Nevertheless, on the peculiar facts of this case, justice is better served by allowing the appeal. We do not consider that the defendant was inexcusably dilatory. When the first judgment was entered it was clearly incorrect; it mentioned on its face that it was entered pursuant to an order which all parties knew had been superseded. It was obvious that the judgment would be corrected so as to comply with the later order of the court, which order was already on file. The judgment was clearly not the final judgment of the court. Even though the defendant should have appealed within 90 days of the first judgment, its appeal was perfected within 90 days of the final judgment and will be allowed.

2. Minn. St. 514.01 gives a lien to certain mechanics, laborers, and materialmen who improve real estate. The extent and amount of this mechanics lien are elucidated by Minn. St. 514.03, which at the time plaintiff's action accrued read in relevant part as follows:

Minn. St. 1971, § 514.03 was revised in L. 1973, c. 247, § 3, effective January 1, 1974, but the relevant matter appears unchanged.

"If the contribution be made under a contract with the owner and for an agreed price, the lien as against him shall be for the sum so agreed upon; otherwise, and in all cases as against others than the owner, it shall be for the reasonable value of the work done, and of the skill, material, and machinery furnished." Minn. St. 1971, § 514.03.

The statute specifically addresses the situation when the contracted project has been completed. In such a case if the lienor has made his contribution under a contract for an agreed price, then the measure of his lien is the sum so agreed upon. Delyea v. Turner, 264 Minn. 169, 118 N.W.2d 436 (1962). In the situation when the project is incomplete, however, the legislature intended that the lien be measured according to ordinary common-law principles. Thus when the project is incomplete the measure of the lien may vary depending on whether the contract was for a specific price, whether the work is substantially complete, whether the plaintiff or the defendant is in breach, and whether the contract is treated as at an end. In this case the district court's findings show that the contract was for an agreed price, that the project was not substantially complete, that the defendant was in breach, and that the plaintiff chose to treat the contract as at an end. In such circumstances, according to the common-law principles of quantum meruit, the lien should be measured by the reasonable value of the fraction of the project that was completed.

The defendant also urges reversal because the district court admitted at the trial documents containing certain information that had not been produced in pretrial discovery. Plaintiff should have produced these documents, but rulings on the admission of evidence are addressed to the sound discretion of the trial court. The court could conclude, as apparently it did, that plaintiff's failure was without prejudice since virtually all of the information in the challenged documents was already available to the defendant.

Affirmed.


Summaries of

E.C.I. Corp. v. G.G.C. Co.

Supreme Court of Minnesota
Jan 2, 1976
306 Minn. 433 (Minn. 1976)

involving issue of whether appeal began to run from the original order or as amended, corrected order

Summary of this case from In the Matter of the Welfare of J.R

In E.C.I. we held that the time limit for taking an appeal was properly computed from the entry of an amended judgment rather than from the original judgment.

Summary of this case from Marzitelli v. City of Little Canada

In E.C.I., the court considered an appeal that was timely if computed from the entry of an amended judgment, but not timely if computed from the entry of the original judgment.

Summary of this case from Kelly v. Kelly

In E.C.I. Corp. v. G.G.C. Co., 306 Minn. 433, 435, 237 N.W.2d 627, 629 (1976), we said, "[T]he time to appeal an issue begins to run anew from a modification of judgment when the issue was for some reason not appealable before the modification."

Summary of this case from Dennis Frandsen Co. v. Kanabec County

In E.C.I. Corp. v. G.G.C. Co., 306 Minn. 433, 435, 237 N.W.2d 627, 629 (1976), we said: "[T]he time to appeal an issue begins to run anew from a modification of judgment when the issue was for some reason not appealable before the modification."

Summary of this case from Krug v. Independent School District No. 16

In E.C.I., the supreme court determined that liens for unfinished work "may vary depending on whether the contract was for a specific price, whether the work is substantially complete,... and whether the contract is treated as at an end."

Summary of this case from Priester Construction Co. v. Hansen

In E.C.I., the court held quantum meruit was the proper measure where the contract was for an agreed price, the project was not substantially complete, the defendant landowner breached, and the plaintiff treated the contract as ended.

Summary of this case from WEST METRO LUMBER v. JOHNSON GENERAL DEV

In E.C.I., the court stated that the legislature intended that when the project is incomplete, "the lien be measured according to ordinary common law principles."

Summary of this case from WEST METRO LUMBER v. JOHNSON GENERAL DEV

stating that "justice [was] better served by allowing the appeal" even though it was untimely

Summary of this case from Swendra v. Nelson

stating time to appeal from judgment "begins at the time that issue first becomes appealable"

Summary of this case from Swendra v. Nelson

In E.C.I. Corp. v. G.G.C. Co., 306 Minn. 433, 435, 237 N.W.2d 627, 629 (1976), the supreme court noted: "[T]he time to appeal an issue begins to run anew from a modification of judgment when the issue was for some reason not appealable before the modification."

Summary of this case from Eager v. Siwek Lumber Millwork, Inc.

In E.C.I., the original order was clearly incorrect, and it was apparent to all parties that it was not the final judgment of the court.

Summary of this case from Swartwoudt v. Swartwoudt

In E.C.I. Corp. v. G.G.C. Co., 306 Minn. 433, 435-36, 237 N.W.2d 627, 629 (1976), the court found that justice was better served by allowing an appeal even though a strict application of the rule would have barred the appeal.

Summary of this case from Kelly v. Kelly
Case details for

E.C.I. Corp. v. G.G.C. Co.

Case Details

Full title:E.C.I. CORPORATION v. G.G.C. CO. AND OTHERS

Court:Supreme Court of Minnesota

Date published: Jan 2, 1976

Citations

306 Minn. 433 (Minn. 1976)
237 N.W.2d 627

Citing Cases

Standard Plumbing Appliance Co. v. Gadtke

The Gadtkes also challenge the findings and conclusions of the district court on waiver. Because the…

Installed Building Solutions v. Allenburg

Again, the price listed in the original building contract was $617,000. Nevertheless, appellants argue that…