From Casetext: Smarter Legal Research

Ctr. for Biological Diversity v. U.S. Bureau of Land Mgmt.

UNITED STATES DISTRICT COURT DISTRICT OF NEVADA
Aug 23, 2017
Case No. 2:14-cv-00226-APG-VCF (D. Nev. Aug. 23, 2017)

Opinion

Case No. 2:14-cv-00226-APG-VCF Case No. 2:14-cv-00228-APG-VCF

08-23-2017

CENTER FOR BIOLOGICAL DIVERSITY, Plaintiff, v. UNITED STATES BUREAU OF LAND MANAGEMENT, et al., Defendants. WHITE PINE COUNTY, et al., Plaintiffs, v. UNITED STATES BUREAU OF LAND MANAGEMENT, et al., Defendants.


ORDER GRANTING IN PART AND DENYING IN PART THE PARTIES' MOTIONS FOR SUMMARY JUDGMENT

(ECF Nos. 87, 93, 97, 99, 107, 110)

The plaintiffs in these consolidated cases challenge the Bureau of Land Management's decision to approve the first phase of a massive water-redistribution pipeline that, when completed, will carry millions of gallons of water from rural areas of eastern-central Nevada to Nevada's most populous county, Clark County. The plaintiffs—the Center for Biological Diversity, Confederated Tribes of the Goshute Reservation, White Pine County, and the Ely Shoshone and Duckwater Shoshone Tribes—all believe that BLM violated several environmental statutes by approving this phase of the project. They move for summary judgment, seeking to halt construction. BLM and Intervenor Southern Nevada Water Authority (the Nevada agency that applied for permission to build this project) both move for summary judgment as well, arguing that BLM properly approved this phase. / / / / / / / /

I am sensitive to the strong feelings and weighty interests at stake in this contest over Nevada's water—after all, in the West, "whisky's for drinkin' and water's for fightin' over." There can be no question that drawing this much water from these desert aquifers will harm the ecosystem and impact cultural sites that are important to our citizens. On the other hand, southern Nevada faces an intractable water shortage. But regardless of whether I think this pipeline is a good or bad idea, my power to review BLM's decision is narrow and set by statute. I must evaluate whether BLM gathered enough information about the project's impacts and used a reasonable, transparent process for determining whether the project should be approved.

Anonymous; often attributed to Mark Twain.

For the most part, I cannot say that BLM violated its duties in approving this portion of the pipeline project. The plaintiffs' primary complaint is that BLM punted the specifics of some of its assessments until later phases of the project. But given that this is a large, complex project that the agency is reviewing in pieces, it must be given some leeway to figure out an efficient and effective way to manage its review as a whole. Courts have acknowledged that agencies need such discretion when reviewing massive projects like this, and it doesn't get much more massive than this 40-year construction project. BLM has determined in its expertise that reviewing this project in phases makes the most sense and that some parts of its review should wait. BLM's decision-making process here was not perfect. But given the scale of this project and the years of development to come, the agency's approval of the first phase of the pipeline was generally not arbitrary or capricious.

That said, there are two narrow areas where I conclude BLM did not meet its obligations. Both involve substantive rules that compel BLM to mitigate certain types of lost habitat. BLM used a sophisticated groundwater model to project how much habitat would be lost, but it failed to explain how BLM or SNWA would mitigate those losses. This omission violated the National Environmental Protection Act's requirement for BLM's Environmental Impact Statement to at least discuss whether and how the project will comply with other environmental rules. I thus remand back to BLM so that the agency can address these narrow deficiencies.

I. Factual Background

A. General overview of the project

This case arises from BLM approving SNWA's application to build a massive pipeline to convey water from Spring, Delamar, Dry Lake, and Cave Valleys in eastern-central Nevada to Las Vegas. This pipeline is a nearly-unprecedented feat of engineering and water reallocation, and stands to move over 27 million gallons of water each year. It will cost billions of dollars and nearly four decades to complete.

SNWA has been developing this project since 1989. Over the last two plus decades, the agency has been working with state and federal authorities on this project as one of several solutions to southern Nevada's longtime water crisis. BLM's role is to decide whether to give SNWA permission to build its pipelines and supporting facilities on federally-controlled land between Clark County and the water aquifers (the underground lakes that will be tapped for the water). But it is the State of Nevada, not the federal government, that must approve SNWA's claim to the water itself.

At that time, SNWA was known as the Las Vegas Valley Water District.

Administrative Record ("AR") 129677, 131372.

For a discussion of the process of states' allocation of water, see Joseph Regalia and Noah Hall, Interstate Groundwater Law Revisited: Mississippi v. Tennessee, 34 Va. Envtl. L.J. 152, 167 (2016) (discussing state control and ownership of water).

BLM's authority to issue a right-of-way (in other words, to allow SNWA to build its pipeline on federal land) comes from three statutes. First, the Federal Land Policy and Management Act (FLPMA) authorizes BLM to manage public lands by balancing various public interests, including environmental, recreational, and other interests like municipal water supply needs. FLPMA requires BLM to consider any applications for rights-of-way to use federal lands for these purposes.

In the next two statutes, Congress specifically directed BLM to approve requests to build water pipelines in Nevada. The Southern Nevada Public Land Management Act (SNPLMA) says that, upon application by a local or regional governmental entity and in accordance with FLPMA and other applicable laws, BLM "shall issue right-of-way grants on Federal lands in Clark County, Nevada" for a pipeline and related facilities for "transportation or distribution of water." The Lincoln County Conservation, Recreation, and Development Act (LCCRDA) states that BLM "shall grant to [SNWA] and the Lincoln County Water District nonexclusive rights-of-way to federal land in Lincoln County and Clark County, Nevada for . . . pipelines . . . that are necessary for the construction and operation of a water conveyance system."

Pub. L. No. 105-263, 112 Stat. 2343 (1998).

Pub. L. No. 108-424, 118 Stat. 2403 (2004).

The project depends on SNWA receiving water rights from the State of Nevada—otherwise, SNWA will have no water to pump. Initially, Nevada's State Engineer granted SNWA over 100,000 afy (acre feet per year) of water. In March of 2012, the State Engineer revised that amount to allow SNWA to pump up to 83,988 afy of groundwater. A few months later, BLM approved SNWA's application for a right-of-way for the first phase of the project, which includes the main pipeline.

AR 188178.

Because of the complexity and scope of this decades-long construction project, BLM decided to review it in phases. BLM's current decision does not approve a right-of-way for any groundwater pumping facilities or other pipelines. Rights-of-way for those facilities would have to be evaluated separately in a process conducted in accordance with the National Environmental Policy Act (NEPA) and FLPMA. BLM is not obligated to grant rights-of-way for those future parts of the project. SNWA will submit separate applications identifying those facilities, and BLM will analyze them on their own. / / / / / / / /

AR 188132. BLM's lawyer agreed during oral argument that approval of SNWA's future applications is not a fail accompli; rather, BLM can deny future applications, and must if they violate applicable laws and rules.

AR 188132.

SNWA's right-of-way for this main pipeline is subject to several terms and conditions, including requirements for mitigation and monitoring. Once SNWA finishes some preconstruction obligations (such as geological surveys), BLM will develop a Construction, Operation, Maintenance, Monitoring, Management, and Mitigation Plan (COM Plan). The COM Plan will address mitigation and monitoring for the construction, operation, maintenance, and abandonment of the main pipeline and subsequent phases of the project. After SNWA has received all necessary approvals from BLM and secured the necessary water rights, construction of the main pipeline, including two lateral pipelines from Cave and Spring Valleys, will take up to five years. Even if all goes as planned, it will take approximately 38 more years for the project to be fully constructed.

AR 188134.

AR 188134-35.

See AR 188341, 188346.

B. BLM's approval of SNWA's first phase of construction, the trunk pipeline, and its high-level programmatic review of the project as a whole

SNWA applied for a right-of-way for this project in August 2004. BLM began reviewing the application in April 2005. It issued a draft Environmental Impact Statement in June 2011 and solicited public comments for 120 days. Because this project is large, complex, and spread out over a number of years, BLM used a tiered approach to analyze the environmental impacts under NEPA. BLM explained that this tiered approach was needed because it does not yet have crucial information, such as the location of the well sites or the precise hydrology and geology of the aquifers. In this first phase and EIS, BLM analyzed the environmental impacts of the construction and operation of the main pipeline, and also analyzed on a "programmatic level" the potential impacts of the completed project in its entirety. In future phases, BLM will conduct site-specific analyses of the environmental impacts of particular groundwater pumping facilities. These future analyses will also revisit the programmatic assessment of the entire project.

AR 129669.

Although the plaintiffs suggested at oral argument that BLM will not revisit its review of the entire project in future EISs, it offers no evidence or analysis to support this contention. BLM is obligated under NEPA to consider all of the impacts of each future stage of the project. And approving, for example, the water extraction facilities will obviously impact the environment in ways similar to the approval of the trunk pipeline at issue here. BLM has confirmed that it will review the project as a whole at each future stage, which will give the public additional opportunities to raise any relevant environmental impacts.

Although the current decision under review approves only the main trunk pipeline, BLM conducted a high-level review of the project as a whole, including the impacts of drawing the water. BLM relied on a computer model of groundwater flow that was developed to evaluate the probable long-term effects of future groundwater withdrawal for the project on a regional scale. The model was reviewed by a team of hydrology experts, including scientists from the United States Geological Survey and independent groundwater modeling experts. The team met several times to develop and hone the model so that it was as accurate as possible. The model considered the hydrogeological framework of the basins, the rate of recharge to the groundwater system, evapotranspiration, and spring flow. BLM assumed it would take 38 years for SNWA to complete the project, and it analyzed potential impacts for three different timeframes: full build out, 75 years after build out, and 200 years after build out.

AR 188141.

AR 188141, 130084-87.

Using this model, BLM simulated the impacts on groundwater based on seven alternatives and an alternative where no pipeline is constructed. These alternatives included the full amount of SNWA's water rights application as well as lesser amounts in accordance with prior rulings by Nevada's State Engineer. The alternatives also varied based on well placement and whether pumping would be conducted in certain valleys. In its final approval of this phase of the project, BLM selected a modified version of Alternative F. Alternative F would have allowed the pumping of 114,129 afy in Spring, Delamar, Dry Lake, and Cave Valleys; the amount of water was based on information presented during the 2011 water rights hearings before the State Engineer. Following the issuance of the State Engineer's water rights ruling in March 2012, BLM revised its modified version of Alternative F by adopting the State Engineer's allocation of 83,988 afy.

After it issued its draft EIS, BLM received 461 comment letters and over 20,000 form letter comments, from federal and state agencies, Indian tribes, and the public. BLM responded to many of these comments. The final EIS was released to the public in August 2012 for a 60-day review period. More than 40 comment letters and 33,000 form letters were submitted during that period, and BLM considered those comments prior to issuing its record of decision approving SNWA's application (the ROD).

AR 188168-69.

AR 188169.

AR 188170-71.

C. Nevada state court proceedings on SNWA's water rights

At the time BLM approved SNWA's right-of-way for the main pipeline, Nevada's State Engineer had authorized SNWA to pump 83,988 afy. Various entities, including White Pine County and the Goshute Tribe, appealed the State Engineer's decision in Nevada state court. That court found that the State Engineer's findings were inadequate and remanded back to the State Engineer. The court instructed the Engineer to: (1) add Millard and Juab Counties in Utah to the mitigation plan for the pumping of groundwater from Spring Valley; (2) recalculate the water available for appropriation from Spring Valley, considering whether the basin would reach equilibrium in a reasonable time; (3) define monitoring and mitigation standards for Spring, Cave, Dry Lake, and Delamar Valleys; and (4) recalculate the water rights appropriations from Cave, Dry, and Delamar Valleys to avoid conflicts with other water users. The State Engineer has not yet revised his findings or SNWA's allocation.

See White Pine County v. King, No. CV 1204049, slip op. (Seventh Judicial Dist. of the State of Nevada, Dec. 10, 2013).

At oral argument, the parties reported that the State Engineer will conduct a hearing in September 2017.

D. BLM's consultations with Nevada's Native American tribes

During the seven years that BLM reviewed SNWA's application, the agency consulted with 28 tribes about the project and its potential impacts. BLM held an open house for the tribes; conducted field visits with an ethnographer; participated at an inter-tribal meeting attended by the Goshute's leaders and lawyers, BLM State Director, and the federal Bureau of Indian Affairs Deputy Regional Director; attended seven other inter-tribal meetings; drafted a comprehensive ethnographic assessment; and received 22 visits from the Ely District's Native American Liaison. BLM also conducted a series of outreach sessions with tribal representatives. BLM detailed its outreach efforts in its EIS.

See AR 189770-190409 (documenting BLM's government-to-government consultation and outreach effort); AR 189782-87 (table summarizing contacts).

See AR 189814-17 (summarizing consultation with Goshute Tribe).

AR 189894-190237 (materials from meetings, trainings, and workshops with tribes).

II. Discussion

A. Standard of review

My review of the plaintiffs' claims is governed by the judicial review provisions of the Administrative Procedure Act (APA). Under the APA, agency decisions may be set aside only if they are "arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law." Review under this standard is "'highly deferential, presuming the agency action to be valid and affirming the agency action if a reasonable basis exists for its decision.'" An agency's decision will be overturned only if the agency relied on factors that Congress did not intend it to consider, failed to consider an important aspect of the problem, offered an explanation for its decision that runs counter to the evidence before it, or is so implausible that it could not be ascribed to a difference in view or the product of agency expertise. The APA "does not allow the court to overturn an agency decision because it disagrees with the decision or with the agency's conclusions about environmental impacts."

5 U.S.C. §§ 701-06; ONRC Action v. BLM, 150 F.3d 1132, 1135 (9th Cir. 1998).

Nw. Ecosystem Alliance v. U.S. Fish & Wildlife Serv., 475 F.3d 1136, 1140 (9th Cir. 2007) (citation omitted).

McFarlane v. Kempthorne, 545 F.3d 1106, 1110 (9th Cir. 2008) (citation and quotation marks omitted); see also Citizens to Pres. Overton Park v. Volpe, 401 U.S. 402, 416 (1971) (role of the reviewing court is to determine whether "the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment").

River Runners for Wilderness v. Martin, 593 F.3d 1064, 1070 (9th Cir. 2010).

Summary judgment is appropriate if there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. My review is based on the agency's administrative record. My role therefore is not to resolve factual issues, but rather to determine whether the agency's record supports its decision under the APA's standard of review.

See Lujan v. Nat'l Wildlife Fed'n, 497 U.S. 871, 883-84 (1990).

See Nw. Motorcycle Ass'n v. U.S. Dep't of Agric., 18 F.3d 1468, 1472 (9th Cir. 1994) ("[T]his case involves review of a final agency determination under the [APA]; therefore, resolution of this matter does not require fact finding on behalf of this court. Rather, the court's review is limited to the administrative record."); see also Occidental Eng'g Co. v. Immigration and Naturalization Serv., 753 F.2d 766, 769 (9th Cir. 1985) (noting that under the APA "the function of the district court is to determine whether or not as a matter of law the evidence in the administrative record permitted the agency to make the decision that it did").

B. The plaintiffs' challenges under NEPA

i. Background

NEPA serves the dual purpose of informing agency decision-makers of the significant environmental effects of proposed major federal actions and ensuring that relevant information is made available to the public so that it "may also play a role in both the decision-making process and the implementation of that decision." NEPA is procedural. "[I]t is now well settled that NEPA itself does not mandate particular results, but simply prescribes the necessary process." "Other statutes may impose substantive environmental obligations on federal agencies, but NEPA merely prohibits uninformed—rather than unwise—agency action."

See Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 349 (1989).

Id. at 350 (citing Stryker's Bay Neighborhood Council v. Karlen, 444 U.S. 223, 227 (1980)).

Id.

To meet the procedural goals of the statute, NEPA requires that an agency prepare a comprehensive EIS for "major Federal actions significantly affecting the quality of the human environment." The Council on Environmental Quality's (CEQ) regulations implementing NEPA provide guidance as to what must be included in an EIS. These regulations direct agencies to include (1) an analysis of alternatives to the proposed action; (2) an analysis of direct, indirect, and cumulative impacts on the environment; and (3) a discussion of ways to mitigate adverse environmental impacts of the proposed action.

See 40 C.F.R. § 1502.

"The reviewing court may not 'fly speck' an EIS and hold it insufficient on the basis of inconsequential, technical deficiencies." Rather, "[o]nce satisfied that a proposing agency has taken a 'hard look' at a decision's environmental consequences, the review is at an end." The critical question is whether the EIS contains a "reasonably thorough discussion of the significant aspects of the probable environmental consequences" of the proposed action as well as a range of alternatives to that action. This "hard look" must be taken objectively and in good faith—"not as an exercise in form over substance, and not as a subterfuge designed to rationalize a decision already made." / / / /

Ass'n of Pub. Agency Customers v. Bonneville Power Admin., 126 F.3d 1158, 1184 (9th Cir. 1997) (citation omitted); see also Swanson v. U.S. Forest Serv., 87 F.3d 339, 343 (9th Cir. 1996); 40 C.F.R. § 1500.3 ("[I]t is the Council's intention that any trivial violation of these regulations not give rise to any independent cause of action.").

Id.

California v. Block, 690 F.2d 753, 761 (9th Cir. 1982).

Metcalf v. Daley, 214 F.3d 1135, 1142 (9th Cir. 2000); S. Coast Air Quality Mgmt. Dist. v. F.E.R.C., 621 F.3d 1085, 1095 (9th Cir. 2010).

At bottom, even if an agency violated NEPA, that does not mean a remedy is necessarily warranted. I must then consider whether any error "materially impeded NEPA's goals—that is, whether the error caused the agency not to be fully aware of the environmental consequences of the proposed action, thereby precluding informed decision-making and public participation, or otherwise materially affected the substance of the agency's decision."

Ground Zero Cir. for Non-Violent Action v. United States Dep't of Navy, 860 F.3d 1244, 1251 (9th Cir. 2017); Idaho Wool Growers Ass'n v. Vilsack, 816 F.3d 1095, 1104 (9th Cir. 2016).

ii. Whether BLM violated NEPA by failing to properly define the purpose and need for the pipeline project

NEPA requires an agency to include in its EIS a statement that "briefly specif[ies] the underlying purpose and need to which the agency is responding." Agencies are afforded "'considerable discretion to define the purpose and need of a project.'" But "an agency may not define the objectives of its action in terms so unreasonably narrow that only one alternative from among the environmentally benign ones in the agency's power would accomplish the goals of the agency's action." Ultimately, the purpose and need statement should "be evaluated under a reasonableness standard."

League of Wilderness Defenders-Blue Mountain Diversity Project v. U.S. Forest Serv., 689 F.3d 1060, 1069 (9th Cir. 2012) (quoting Friends of Southeast's Future v. Morrison, 153 F.3d 1059, 1066 (9th Cir. 1998)); see also Westlands Water Dist. v. U.S. Dep't of the Interior, 376 F.3d 853, 866 (9th Cir. 2004).

Nat'l Parks & Conservation Ass'n v. Bureau of Land Mgmt., 606 F.3d 1058, 1070 (9th Cir. 2010) (citation omitted); see also City of Carmel-by-the-Sea v. U.S. Dep't of Transp., 123 F.3d 1142, 1155 (9th Cir. 1997).

Friends of Southeast's Future, 153 F.3d at 1066-67.

BLM sensibly states in the EIS that the "purpose for this [right-of-way] action is to consider the applicant's request for use of federal land managed by BLM for construction and operation of the proposed groundwater conveyance system," and that the need "arises from its responsibility under FLPMA and other legislation to respond to the applicant's [right-of-way] request." BLM did not narrow the purpose or need for its action: it was required to consider whether a pipeline project should be approved to redistribute water in Nevada, and that is what it did. This is particularly true given that Congress directed BLM to review and approve water pipeline projects in this corridor. And BLM did not frame its purpose so narrowly that it was unable to consider alternatives—indeed, it considered a number of them.

AR 129671.

White Pine County argues that BLM improperly narrowed its purpose and need statement by taking the position that it must approve SNWA's application. White Pine suggests that BLM failed to "genuinely" review SNWA's application because the agency believed it had to approve regardless of what its review revealed. But there is no evidence that BLM intended on approving the project regardless of the consequences. While it is true that BLM noted that two statutes required it to approve right-of-way requests like SNWA's, the statutory provisions the agency relied on say that this approval depends on whether other statutes, including NEPA, are satisfied. BLM never indicated that it would approve this pipeline regardless of the outcome of its NEPA analysis. Indeed, the agency conducted an extensive review and analysis of environmental and other impacts. BLM even considered a no-action alternative, meaning it considered not approving the project at all. This review belies White Pine's argument that the agency was merely acting under pretext. / / / / / / / / / / / /

AR 188126.

See Alaska Survival v. Surface Transp. Bd., 705 F.3d 1073, 1085 (9th Cir. 2013) ("[A]n agency must consider the statutory context of the proposed action."); Honolulutraffic.com v. Fed. Transit Admin., 742 F.3d 1222, 1230 (9th Cir. 2014) (upholding a purpose and need statement that was "defined in accordance with the statutorily mandated formulation of [a] transportation plan"); see also Protect Our Communities Found. v. Jewell, Case No. 13cv575 JLS (JMA), 2014 WL 1364453, at *5 (S.D. Cal. Mar. 25, 2014) (upholding a purpose and need statement regarding a renewable energy project where the statement was consistent with "the statutory, executive, and administrative directives invoked by BLM").

iii. Whether BLM violated NEPA by inadequately considering alternatives to the selected project

NEPA requires agencies to consider in detail alternatives to a proposed action. In the final EIS, BLM considered six groundwater pumping and conveyance alternatives, as well as a no-action alternative. White Pine County contends that BLM's unduly narrow purpose and need statement caused it to disregard viable alternatives. The County proposes alternatives, including Colorado River management measures, increased water conservation measures, and desalination facilities. The County contends BLM did not seriously consider these alternatives, restricting its analysis to the narrow band of variations of the project it ended up approving. The County does not, however, argue that BLM gave short shrift to alternatives that were within the scope of its statement of purpose and need. BLM responds here, as it did in rejecting the County's proposed alternatives in the EIS, that those alternatives did not meet BLM's articulated purpose and need. BLM adds that it otherwise considered all feasible alternatives that could satisfy the purpose of the project. The agency was not arbitrary in determining that none of the alternatives proposed by White Pine County would meet that purpose.

ECF No. 98 at 35-36.

Id. at 36.

ECF No. 107-1 at 37-38.

Even if BLM had adopted White Pine County's preferred framing of the project—meeting the water needs of Southern Nevada—it reasonably concluded that none of the County's alternatives was feasible. Modifications of Colorado River allocations would require an act of Congress. BLM found that water conservation would be inadequate to satisfy the region's needs. A desalination project would be highly expensive, technically difficult, and would also require modification of Colorado River allocations. SNWA points out that none of these alternatives would meet its need to reduce its current overwhelming reliance on the Colorado River for water. BLM thus met its NEPA obligation to "[r]igorously explore and objectively evaluate all reasonable alternatives, and for alternatives which were eliminated from detailed study, briefly discuss the reasons for their having been eliminated."

Id. at 38.

ECF No. 109 at 40.

40 C.F.R. § 1502.14(a).

iv. Whether BLM violated NEPA by failing to take a hard look at the cumulative impacts on the environment and the impacts of climate change

The plaintiffs suggest that BLM did not take a hard-enough look at the environmental impacts of the project as a whole, including the extent to which climate change might amplify those impacts. Courts are "most deferential when reviewing scientific judgments and technical analyses within the agency's expertise under NEPA" and will not "impose [ourselves] as a panel of scientists." The scope of an environmental analysis, "in addition to the extent and effect of the cumulative factors[,] is a task assigned to the special competency of the appropriate agencies." Agencies have "discretion to determine the physical scope used for measuring environmental impacts" so long as they do not act arbitrarily and their "choice of analysis scale . . . represent[s] a reasoned decision."

See Native Ecosystems Council v. Weldon, 697 F.3d 1043, 1051 (9th Cir. 2012) (internal citations and quotation marks omitted).

Kleppe v. Sierra Club, 427 U.S. 390, 414 (1976) (concluding that Interior's choice to limit scope of comprehensive statement was not arbitrary despite Respondent's argument that a comprehensive statement on the whole region was required because all coal-related activity was programmatically, geographically, and environmentally related); Neighbors of Cuddy Mtn. v. Alexander, 303 F.3d 1059, 1071 (9th Cir. 2002) ("Under NEPA, we defer to an agency's determination of the scope of its cumulative effects review.").

WildWest Institute v. Bull, 547 F.3d 1162, 1173 (9th Cir. 2008) (quoting Idaho Sporting Cong., Inc. v. Rittenhouse, 305 F.3d 957, 973 (9th Cir. 2002)).

The plaintiffs first challenge BLM's analysis of the pipeline's impacts to the environment generally. But the plaintiffs have not shown that BLM's methodologies in analyzing the impacts were arbitrary or capricious. The EIS contains a thorough discussion of the potential impacts of pumping groundwater over the long term. BLM largely relied on the groundwater flow model discussed above. BLM based its model on similar models that have been made of the affected regions. The model team considered a variety of information, including field studies.

Notably, the precise contours of BLM's model is entitled to deference. See Marsh v. Or. Natural Res. Council, 490 U.S. 360, 378 (1989) ("An agency must have discretion to rely on the reasonable opinions of its own qualified experts . . . ."); see also Lands Council v. McNair, 537 F.3d 981, 993 (9th Cir. 2008) (en banc) ("We are to be most deferential when the agency is making predictions, within its area of special expertise, at the frontiers of science.") (citations and quotation marks omitted).

The plaintiffs suggest that BLM was arbitrary in limiting its analysis to areas that are likely to experience at least a 10-foot decrease in groundwater level. But BLM offers reasons for limiting its analysis to these areas, including the large scale of the model and the natural fluctuations of groundwater. BLM's experts concluded that a lower limit would make it difficult to determine which impacts were caused by the water drawdown and which were caused by other natural factors. And the plaintiffs offer no specific argument why this reasoning is arbitrary or why a different limit is better. BLM is entitled to deference in determining the appropriate contours of its model.

The plaintiffs also argue that BLM should not have limited its analysis to 200 years in the future. But an agency has wide discretion to determine the appropriate scope of its review. "NEPA does not impose a requirement that [an agency] analyze impacts for any particular length of time." The plaintiffs offer no concrete reasons why a different time period is necessary.

Selkirk Cons. Alliance v. Forsgen, 336 F.3d 944, 962 (9th Cir. 2003).

The plaintiffs' primary argument is that BLM should have given greater consideration to how climate change might affect the environmental impacts of the pipeline project. In other words, BLM's models should have assigned a quantitative measure for climate change's effects on the impact the pipeline project will have.

But BLM adequately considered the impacts of climate change in approving SNWA's right-of-way. BLM considered "global climate change and regional climate change trends." It noted that global surface temperatures have risen and will continue to rise in the future. And it considered the climate history for the regions directly impacted by the pipeline. Then BLM analyzed the cumulative impact of climate change combined with the pipeline project. The EIS concludes that "[g]reater variability in patterns of precipitation can be anticipated," and an increase in global temperatures over the next century could be associated with an increase in the frequency of extreme weather events, such as drought, heat waves, and wildfires.

AR 129855-56.

AR 129910-12, 129985, 130209, 130260, 130356-57, 130520, 130632-33, 130684, 130724, 130753, 130769, 130819, 130856, 130896, 130957, 130985, 131032, 131151, 131174.

AR 130209.

The plaintiffs contend that it was not enough for BLM to generally consider the fact that climate change might amplify harm to the environment, but that it was required to include specific climate change data. But nothing in NEPA or the relevant case law suggests that is the case. The proper question is whether BLM acted arbitrarily when it determined that it was preferable to broadly consider the impacts of climate change rather than quantitatively considering its impacts. The plaintiffs fall short on this point, failing to point to any hard data that BLM should have incorporated into its analysis. BLM concluded in its expertise that the climate change data before it was not reliable enough to feed into its models, and there is no evidence that this was an arbitrary decision. For example, there were no studies or evidence quantifying the impact of climate change on groundwater. BLM's decision to consider climate change's impacts qualitatively, and to not include its impacts quantitatively in its models, was thus not infirm.

Friends of the Wild Swan v. Jewell, Case No. CV 13-61-M-DWM, 2014 WL 4182702 (D. Mont. Aug. 21, 2014); S. Utah Wilderness Alliance v. Burke, 981 F. Supp. 2d 1099, 1110-11 (D. Utah 2013) (finding that BLM's analysis of cumulative impacts sufficiently addressed the combined impacts of off-highway vehicle use and climate change).

The CEQ's guidance on climate change suggests that agencies should consider its impacts, but it does not indicate that agencies are required to quantify those impacts or specifically predict the precise changes it will bring.

v. Whether BLM inadequately considered impacts on cultural and religious sites

The plaintiffs argue that BLM did not adequately consider how the pipeline would impact Native American cultural sites. But the record reveals that the agency thoroughly considered the pipeline's potential impacts on these sites, which is what NEPA requires. BLM analyzed impacts on culturally significant plants and animals, including plant species identified by the tribes through consultation. These impacts are described in the vegetation section of the EIS, which identifies impacts to culturally sensitive plants, their habitat, and wildlife that consume them. The EIS discusses the cultural and spiritual significance of water to the Goshute Tribe and the tribe's objections to the groundwater pumping. The EIS explains how the 76 possible sites with religious and cultural significance might be affected. Indeed, BLM identified several important cultural sites while consulting with the tribes, and recommended those for designation on the National Register as Traditional Cultural Property. The EIS also discusses potential ways to mitigate harm to cultural sites.

AR 130991-131038.

AR 131001.

AR 130288, 130290-130297, 130314, 130362, 130366, 131011, 131015-17.

AR 131001-03, 131017.

AR 131006.

AR 190479-81.

BLM again notes in the EIS that it did not do a more thorough analysis of potential impacts on cultural sites because it does not yet have all the information it needs (such as the location of the well sites), and that it will address additional concerns in later EISs as the project progresses. This is a reasonable approach. The tribes have not otherwise identified any property, site, or cultural resource that was omitted from or insufficiently analyzed in the EIS.

vi. Whether BLM impermissibly "segmented" its NEPA analysis

White Pine County argues that BLM's "tiered" approach to its NEPA analysis was an improper attempt to "segment" its analysis such that the full impact of the project is not apparent in any one analysis. The County argues this approach was unreasonable, given that the general contours of the project, as well as many of the specifics, have been established. It contends that subsequent site-specific analyses will be "piecemeal," robbing BLM and the public of the opportunity to reevaluate the entire project in light of the new information. It also argues that the current approval will set BLM on a path to "irreversible and irretrievable commitment of resources to the Project," undercutting the utility of subsequent NEPA analyses.

ECF No. 98 at 29-31.

Id.

BLM responds that CEQ regulations authorize agencies to use tiered analysis for complex projects where not enough information is known about later stages of a project to perform a uniform, in-depth analysis at the beginning. BLM argues that its tiered process provided specific analysis of the parts of the project on which it had sufficient information to do so, conducted broad-stroke programmatic analysis of the overall project, and deferred site-specific analysis of later components. BLM also assures that, in the course of later site-specific analyses, it will not employ a piecemeal approach but will instead reevaluate the project holistically. BLM adds that the only "irretrievable" commitment of resources at this point is to the main pipeline, which was fully analyzed in this first phase; subsequent analyses could cause BLM to deny SNWA authority to actually draw groundwater.

ECF No. 107-1 at 39 (citing 40 C.F.R. § 1502.20).

ECF No. 124 at 21.

"Tiering . . . is appropriate when it helps the lead agency to focus on the issues which are ripe for decision and exclude from consideration issues . . . not yet ripe." BLM has "flexibility in deciding the level of analysis to be performed at a particular stage." In a case similarly involving "many separate sub-projects [that] will take many years" to complete, a court approved an agency's decision to issue a programmatic analysis on the front end, leaving site-specific analyses for later. BLM estimates this entire project will take 38 years to complete, and the "actual plans for the development of future pumping facilities have not yet been developed." BLM made assumptions about well placements in order to complete its broad programmatic analysis, but it does not follow that BLM was required to conduct site-specific analyses based on those speculative assumptions.

40 C.F.R. § 1502.28(b).

Native Vill. of Point Hope v. Jewell, 740 F.3d 489, 498 (9th Cir. 2014).

See Nevada v. Dep't of Energy, 457 F.3d 78, 91-92 (D.C. Cir. 2006).

ECF No. 107-1 at 40, 45.

White Pine County also fails to rebut BLM's assertion that it retains authority to block groundwater extraction generally and at specific well sites. The County's argument that BLM is making an irreversible and irretrievable commitment of resources is thus undermined. Further, the EIS explains that future NEPA reviews will also update impact assessments at the basin-wide level. Because BLM has reasonably explained the motivation for and manner in which it tiered the project, it did not violate NEPA in so doing.

ECF No. 125 at 22.

vii. Whether BLM violated NEPA by inadequately considering mitigation measures

An EIS must, in addition to enumerating environmental effects, include "a reasonably complete discussion of possible mitigation measures." The plaintiffs argue BLM's discussion of mitigation was inadequate under NEPA because BLM failed to provide and analyze "thresholds or triggers" for when additional mitigation would be necessary. BLM responds that its discussion of mitigation measures was appropriately detailed, and that no authority requires it to provide thresholds for additional mitigation.

Okanogan Highlands Alliance v. Williams, 236 F.3d 468, 473 (9th Cir. 2000).

ECF No. 88 at 33-36; ECF No. 98 at 40-42.

ECF No. 107-1 at 46-56.

An EIS's discussion of mitigation measures enables both the agency and the public to "properly evaluate the severity of the adverse effects." The EIS must also assess whether proposed mitigation measures can be effective. These requirements do not impose, however, a "substantive requirement that a complete mitigation plan be actually formulated and adopted."

Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 352 (1989).

S. Fork Band Council of W. Shoshone of Nevada v. U.S. Dep't of Interior, 588 F.3d 718, 727 (9th Cir. 2009).

Id.

In this case, the discussion of possible mitigation measures in the EIS was reasonable under NEPA for the first stage of the tiered project. BLM's approach to mitigation on this project was to enter into stipulations with SNWA committing to monitor and mitigate if groundwater rights are developed. Those agreements contain detailed requirements for SNWA to collect baseline data, so that it may establish early warning thresholds to mitigate project impacts. A table describing dozens of proposed mitigation measures is provided in the EIS. The EIS also describes project-wide mitigation measures that could be employed to address excessive groundwater drawdown, including "geographic redistribution of groundwater withdrawals," "reduction or cessation in groundwater withdrawals," "recharge projects to offset local groundwater drawdown," and "implementation of cloud seeding programs to enhance groundwater recharge." Courts have repeatedly upheld agencies' choices to defer specific mitigation plans for complex projects where subsequent, site-specific choices were still inchoate. The plaintiffs seek to distinguish those cases, but do not point to a case where an agency pursuing a legitimately tiered project was required to do more than BLM did here at the first stage.

AR 131424-509.

Id.

AR 131176-193.

AR 130119.

See, e.g., N. Alaska Envtl. Ctr. v. Kempthorne, 457 F.3d 969, 979 (9th Cir. 2006); Okanogan Highlands, 236 F.3d at 473-77; City of Carmel-by-the-Sea v. U.S. Dep't of Transp., 123 F.3d 1142, 1154 (9th Cir. 1997).

BLM also satisfied its requirement to assess, at least tentatively, how effective the proposed mitigation measures are likely to be. The requirement is not a precise one and certainly does not require development of, or commitment to, a complete mitigation plan. BLM explained that the monitoring and mitigation plan "will likely reduce potential impacts to critical areas but would not entirely eliminate impacts to water dependent resources." BLM also acknowledged that the "recovery of water levels . . . to pre-project conditions could take several years or decades." Additionally, BLM conceded that

Robertson, 490 U.S. at 352.

AR 130123.

AR 132707.

a long-term reduction in surface discharge at perennial surface water source areas is likely to occur in some areas even after implementation of the SNWA proposed adaptive management measures and proposed mitigation measures. This potential reduction in surface discharge at perennial surface water source areas is considered an unavoidable adverse impact associated with the proposed groundwater development.
It is true that EPA sought more specificity from BLM about thresholds for additional mitigation and likely effectiveness. Besides taking EPA's comments seriously, however, BLM was not statutorily bound to comply. It is important to clarify that some of the concerns voiced by the Center for Biological Diversity and EPA seem to be that environmental impacts will not be completely mitigated, or more broadly that the harms of the project outweigh the benefits. This does not state a NEPA complaint, so long as BLM was appropriately forthright as to what those impacts are likely to be. BLM was within its discretion to conclude that the best approach was to offer a broad discussion of mitigation in the programmatic analysis, followed by development of a specific plan that will precede any approvals that actually allow groundwater extraction.

AR 130129.

viii. Whether BLM violated NEPA by refusing to prepare a supplemental EIS

The plaintiffs contend that BLM violated NEPA by failing to prepare a supplemental EIS once it was informed of new information about the project's impacts on the environment. BLM is required to prepare a supplemental EIS if there "are significant new circumstances or information relevant to environmental concerns and bearing on the proposed action or its impacts." "[A]n agency need not supplement an EIS every time new information comes to light after the EIS is finalized"; if that were the requirement, "agency decisionmaking [would be] intractable, always awaiting updated information only to find the new information outdated by the time a decision is made." Instead, a supplement is required only if "new information shows that the remaining action will affect the quality of the human environment in a significant manner or to a significant extent not already considered."

Marsh, 490 U.S. at 373.

Id.

Or. Nat. Res. Council Action v. U.S. Forest Serv., 445 F. Supp. 2d 1211, 1219 (D. Or. 2006) (citing Marsh, 490 U.S. at 374).

Additionally, to require the agency to prepare a supplemental report, the new information must bear on federal actions not yet taken. The supplementation requirement is meant to ensure that the agency takes a hard look at any new information that might impact the agency's future decision-making. The agency must therefore still be poised to take "major Federal actio[n]" on the prior EIS and the information must be significant enough to potentially impact the agency's future decisions. Otherwise, the agency is under no obligation to prepare a supplement.

Id.

I may overturn an agency's decision not to prepare a supplemental EIS only if it was arbitrary or capricious. Whether new information is significant enough to warrant a supplement turns on technical expertise and underlying factual determinations, and therefore the agency is best positioned to decide.

Id.

Id.

BLM has no substantive decisions left to make on the first phase of the project, so a supplemental EIS is of little use. As explained above, whether a supplement is required "turns on the value of the new information to the still pending decision-making process." As to this first phase (the main pipeline right-of-way), BLM has little decision-making to do. It still must issue a final Notice to Proceed and a monitoring plan, but these are merely to ensure that SNWA complies with the terms of the existing approval. BLM will prepare new EISs at each phase of the project, and those EISs will ensure that the agency considers any new data that the plaintiffs are concerned about. The plaintiffs provide no authority suggesting that anything BLM has left to do on this first phase triggers the duty to supplement. The one case they rely on, Bundorf v. Jewell, is distinguishable because there BLM had not yet issued the right-of-way, so major federal decision-making remained.

Ctr. for Biological Diversity v. Salazar, 706 F.3d 1085, 1095 (9th Cir. 2013).

142 F. Supp. 3d 1138, 1151 (D. Nev.), appeal dismissed (June 8, 2016), clarified on denial of reconsideration, 142 F. Supp. 3d 1133 (D. Nev. 2015), appeal dismissed (June 8, 2016), appeal dismissed (Oct. 26, 2016).

What the plaintiffs really seek is for BLM to reconsider its prior decision and retroactively void its prior approval. But that is not a proper basis for a supplemental report. Because the first phase of the project has been approved, and because future phases will be separately reviewed based on whatever new information exists at that time, I cannot say BLM abused its discretion in declining to prepare a supplement to its initial EIS.

But even if BLM still had sufficient decisions left to make on its initial EIS, the plaintiffs have not provided significant new information warranting a supplemental report.

a. The Nevada court's reversal of the State Engineer's findings

Both the Center for Biological Diversity and White Pine County argue that BLM was obligated to prepare a supplemental EIS based on the state court decision in White Pine County v. King, which remanded the State Engineer's water rights allocation. But the state court ruling has caused neither substantial changes for the pipeline nor brought to light significant new information about the environmental impacts of the pipeline.

The state court found flaws in SNWA's mitigation agreements, that the appropriations from three sites had been double allocated, and that removing this much water from the planned well sites might not be in the public's interest. But these findings add little to BLM's decision-making process. First, the state court's findings are not binding on BLM. Second, and more importantly, the state court proceeding has not yet finished and the State Engineer has not issued any new findings. Even if BLM wanted to draft a supplemental EIS, there is no new data about SNWA's allocation of water. At best, the plaintiffs' argument on this point is not yet ripe and would need to be filed if SNWA's water allocation actually changes. Third, that there were some problems with the State Engineer's findings is not "significant" new data that might inform BLM's decision-making going forward, given that the errors do not reveal any quantifiable problems with the data that BLM considered (at least at this stage).

b. SNWA's most recent water resource plan

The plaintiffs next argue that SNWA's new plan for water allocation constitutes significant new data that BLM must analyze. SNWA has revised its allocation plan several times. Its plan in 2004 was to start building the pipeline in 2006. SNWA's 2009 plan, which BLM relied on in approving the right-of-way, planned to break ground on the pipeline in 2009 and complete it in 2020. SNWA's 2015 plan suggests that there is a possibility that water from the pipeline may not be needed until several years later than SNWA previously thought.

ECF No. 89-4.

SNWA's 2015 plan offers some helpful data to BLM. It indicates that the population in southern Nevada may not grow as anticipated and that SNWA may not need as much water as soon as it thought it might. But this is not enough to trigger a supplemental EIS. SNWA's new plan merely suggests that it may be able to wait longer to draw water from the pipeline; it does not suggest that the pipeline is not needed. The pipeline project is a long-term endeavor, and the precise date that water will be needed, and the precise amount that will be sufficient to meet southern Nevada's needs, is impossible to tell this far out. BLM and SNWA estimated SNWA's needs at the time BLM made its decision. But the data will continue to fluctuate over the many decades it will take to complete this project. Only when new significant data comes to light would BLM be compelled to supplement.

c. Climate change data

The plaintiffs claim that new climate change studies warrant a supplemental EIS. The first study is entitled, "Assessment of Climate Change in the Southwest United States" and was issued in 2013. The plaintiffs contend that BLM must supplement to consider the study's findings that drought will be more frequent and intense than previously thought and that climate change is more certain now. The plaintiffs also offer a 2015 report by NASA, which similarly concludes there will be an increased risk of drought in the Southwest. The Ninth Circuit has deferred to an agency's decision that new climate change data is not relevant to its actions, so long as the agency's explanation is not arbitrary.

AR 191583.

Wild v. Connaughton, 662 F. App'x 511, 515 (9th Cir. 2016) (rejecting NEPA challenge based on new climate change studies because the plaintiffs failed to explain why the agency's discounting of these studies was arbitrary); Oregon Wild v. Constance Cummins, No. 1:15-CV-01360-CL, 2017 WL 923917, at *4 (D. Or. Mar. 8, 2017).

Here BLM has adequately considered the impacts of climate change on its decision, and these new studies add nothing significantly new. The plaintiffs' real issue is with BLM's decision to not include quantitative data for climate change in its modeling and calculations. As discussed above, BLM decided to consider climate change's impact qualitatively because it determined that there was not enough hard data on the likely impact of climate change on groundwater systems. Nothing in these two studies suggests otherwise. These studies provide no new, raw data about how climate change might affect the pipeline's environmental impact. They conclude that climate change is likely to increase drought and rising temperatures, and BLM already qualitatively considered this in its EIS.

White Pine also suggests that BLM must consider new data about water supplies and SNWA's potential to obtain water by desalinizing ocean water. But there is virtually no evidence that either of these issues has any meaningful impact on BLM's decision in this case. Finally, the plaintiffs complain that BLM adopted a final decision, modified Alternative F, which was not in the original draft EIS. But the approach BLM adopted was within the range of alternatives in the original EIS, so it is permissible. Russell Country Sportsmen v. U.S. Forest Serv., 668 F.3d 1037, 1045 (9th Cir. 2011).

ix. Whether BLM violated NEPA by failing to evaluate compliance with the Clean Water Act Section 404(b) guidelines and compensatory mitigation rule

Although BLM's analysis of the project is mostly sound under NEPA, the same cannot be said of the agency's consideration of whether the project will comply with the Clean Water Act. NEPA requires that agencies not only analyze the direct environmental impact of a project, but also whether that project will comply with other substantive laws, such as the CWA. The Center for Biological Diversity notes that the EIS predicts destruction of thousands of acres of wetlands, but fails to address how BLM or SNWA will meet the CWA requirement to compensate for those losses elsewhere. This omission, the Center for Biological Diversity contends, violates NEPA's requirement to discuss whether and how the project will comply with other environmental laws and policies. BLM responds that the CWA issue is unripe because SNWA has not yet applied for a CWA permit and the Army Corps of Engineers has not stated what compensatory mitigation it would require.

ECF No. 88 at 36-38.

Id. at 36 (citing 40 C.F.R. § 1502.2(d)).

Id. at 57-58. The Army Corps of Engineers reviews permits for activities that may detrimentally affect "waters of the United States" under Section 404 of the CWA.

An EIS "shall state how alternatives considered in it . . . will or will not achieve the requirements of . . . other environmental laws and policies." The EIS indicates that the project, when fully complete, will result in the long-term, and perhaps permanent, loss of many acres of wetlands. Pursuant to its permitting authority under the CWA, the Army Corps of Engineers will likely require SNWA to compensate for lost wetlands within the same watershed in a manner "sufficient to replace lost aquatic resource functions" at "a minimum one-to-one . . . compensation ratio."

AR at 130350.

BLM responds that it is not clear at this stage exactly what the Corps will require of SNWA, even if SNWA proceeds with groundwater extraction and the resulting wetlands losses. There are different types of CWA Section 404 permits, and the Corps has some latitude in designing compensatory mitigation requirements. BLM therefore posits it is premature to assess the feasibility of compliance and adds that it will have the opportunity to evaluate the prospects for Section 404 compliance in subsequent NEPA reviews once SNWA has gone through the Corps' permitting process.

ECF No. 107-1 at 57.

ECF No. 107-1 at 57.

But just because BLM is uncertain about the precise compensation the Corps will require does not mean that the agency can entirely ignore its responsibility to analyze whether alternatives "will or will not achieve the requirements of" the CWA. While the controlling regulations give the Corps some discretion in designing permits, they still mandate that lost wetlands be fully mitigated to the greatest practicable extent. It was therefore unreasonable for BLM to embark on this project without determining, at least in broad strokes, how SNWA would replace or restore wetlands impacted by the project (or even whether compensating for thousands of acres of destroyed wetlands is possible in the first place). Assuming that the Corps does require compensation in line with the CWA's terms—and BLM offers no concrete reason to think it won't—it was arbitrary for BLM to approve major construction on this project without some consideration of how SNWA might comply with the CWA. BLM must address this issue on remand.

C. Challenges under FLPMA

i. Background

FLPMA directs BLM to inventory federal public lands and coordinate with other agencies about how to manage those lands in a productive way. This statute instructs that in so managing, BLM must balance environmental, ecological, and recreational interests while also providing for "multiple use and sustained yield" of the land.

FLPMA's definition of "multiple use" calls for the "combination of balanced and diverse resource uses that takes into account the long-term needs of future generations for renewable and nonrenewable resources, including, but not limited to, recreation, range, timber, minerals, watershed, wildlife and fish, and natural scenic, scientific, and historical values . . . ." FLPMA affords BLM the discretion to determine which combination of uses "will best meet the present and future needs of the American people."

Id. § 1702(c).

Id.; see also Norton v. S. Utah Wilderness All., 542 U.S. 55, 57 (2004).

BLM is required to develop land use plans specific to particular geographic areas. BLM's land use plans set goals and standards to guide its future decisions in that region. BLM is required to "manage the public lands . . . in accordance with the land use plans."

43 U.S.C. § 1732(a); 43 C.F.R. § 1610.5-3; see also Or. Natural Desert Ass'n v. BLM, 625 F.3d 1092, 1097 (9th Cir. 2010).

FLPMA allows BLM to grant rights-of-way across public lands for various uses, including pipelines for the transportation of water. "In determining the duration of the right-of-way, the [BLM] shall, among other things, take into consideration the cost of the facility, its useful life, and any public service it serves."

ii. FLPMA claim for failure to comply with the Ely Resource Management Plan

The plaintiffs claim BLM violated FLPMA because the pipeline project does not comply with a land use plan the agency created: the 2008 Ely Resource Management Plan (RMP). They claim the EIS acknowledges the destruction of special status species habitat, aquatic habitat, sagebrush habitat, and vegetation, but fails to explain how the project will meet the compensatory mitigation and other protective requirements imposed by this RMP. They also complain that BLM has inappropriately limited its analysis of RMP compliance to the main pipeline (the first phase of the project discussed in the NEPA section above), ignoring the RMP compliance threats from subsequent project stages.

ECF No. 88 at 38-44; ECF No. 98 at 48-49.

They complain, though, that BLM is inadequately precise with respect to some habitat losses. See ECF No. 88 at 41.

BLM responds that it has ensured the first phase of the project complies with the Ely RMP, and that it will "refine[]" project terms and conditions for later phases. BLM also contends that the plaintiffs significantly overstate the amount of habitat loss projected in the EIS. To the extent that BLM elected mitigation alternatives that differ from those laid out in the RMP, BLM asserts it has the discretion to do so. As to limiting its discussion of RMP compliance to the first phase of the project, BLM says FLPMA contains no requirement to preemptively ensure compliance for subsequent, related parts before taking action on a preliminary phase.

ECF No. 107-1 at 77.

Id. at 77-78.

Id. at 79-81.

ECF No. 124 at 53-54.

While RMPs are "designed to guide and control future management actions," BLM has "a great deal of discretion in deciding how to achieve compliance with an RMP." This discretion is a necessary function of BLM's task to balance multiple uses for land in a way to best meet the needs of the American people. BLM may not, however, take actions "inconsistent with the provisions of a land use plan." In addition, an RMP may contain language that "creates a commitment binding on the agency."

Klamath Siskiyou Wildlands Ctr. v. Gerritsma, 962 F. Supp. 2d 1230, 1235 (D. Or. Aug. 21, 2013), aff'd, 638 F. App'x 648 (9thCir. 2016) (quoting Norton, 542 U.S. at 66).

Norton, 542 U.S. at 69.

Id. at 71.

Most of the plaintiffs' complaints about how BLM chose to comply with the Ely RMP do not describe an abuse of discretion. For instance, BLM was entitled to determine that only nesting habitats for avian and bat species need to be replaced, rather than the more wide-ranging foraging habitats. BLM was also well within its permitted discretion in how it addressed broad directives to protect vegetation, strategies that it incorporated in the terms of its right-of-way and will incorporate into its COM Plan. The EIS does not specifically address the RMP's requirement to preserve sagebrush habitats, but does explain how BLM will preserve habitats for sagebrush-dependent animals. Because BLM plausibly asserts those are the same habitats, it was adequate for BLM to provide only one analysis. Although a closer question, BLM was also entitled to decide that temporarily disturbed habitat (even for up to 200 years) need not be mitigated and that only permanently-lost habitat must.

See ECF No. 107-1 at 78.

See id. at 83-83.

See ECF No. 124 at 62.

See ECF No. 107-1 at 77-78.

On the other hand, the RMP's requirement that BLM replace certain lost habitats (special status species, aquatic species) at a 2-to-1 ratio is a clear, binding commitment on the agency. BLM responds that it included that requirement in its right-of-way grant to SNWA for some of the species. For those species, BLM has met its FLPMA obligation. The statute does not impose on BLM the additional burden of elaborating how SNWA will comply, and the case cited by the Center for Biological Diversity does not support the proposition.

See id. at 78-79.

See id. at 79.

See ECF No. 88 at 42-43 (citing Or. Natural Res. Council v. Brong, 492 F.3d 1120, 1131-32 (9th Cir. 2007)).

But BLM did not impose obligations on SNWA to comply with the 2-to-1 mitigation requirement for all the special status species habitats. It instead asserts that the RMP requires BLM to apply compensatory mitigation on a "project-by-project basis" and reiterates that BLM has discretion in interpreting RMPs. / / / /

See ECF No. 107-1 at 79-81.

Neither point addresses the clear RMP requirement to replace lost habitat at a 2-to-1 ratio. The phrase "[o]n a project by project basis" may be amenable to different reasonable interpretations, but that the requirement is optional is not one of them. BLM therefore has not complied with FLPMA with respect to special status species that will lose habitat due to construction of the main pipeline. There is also the prospect of future FLPMA violations for BLM's failure to require 2-to-1 mitigation for special status species and aquatic habitats lost due to groundwater pumping. While premature as a complaint under FLPMA, this presents the same NEPA problem as BLM's failure to explain how it might comply with Section 404 of the CWA. On remand, BLM must consider how it might ensure compliance for all phases of the project with the clear-cut compensatory mitigation requirements established by the Ely RMP.

BLM points out that desert tortoise habitat is granted a special carve-out in the RMP from the 2-to-1 mitigation requirement, and suggests that "if alternative measures may be applied to the desert tortoise, it is reasonable for BLM to determine that alternatives to 2:1 compensatory mitigation may be applied to other species . . . ." ECF No. 124 at 54. On the contrary, the provision of a specific exception for desert tortoises suggests that BLM does not have general discretion to ignore the requirement.

iii. FLPMA claim for authorizing a permanent right-of-way in White Pine County

The plaintiffs argue FLPMA limits BLM's authority to issue a right-of-way in perpetuity, requiring instead that the agency limit rights-of-way to a specified period of time. BLM's authority here comes from 43 U.S.C. § 1764, FLPMA's "general requirements" section for issuing rights-of-way. This section does not limit BLM's authority to issue permanent rights-of-way, but requires only that the agency determine what a reasonable period would be under the circumstances, considering "the cost of the facility, its useful life, and any public purpose it serves." Nothing prevents BLM from determining that in any given project a permanent right-of-way is the most reasonable term under the circumstances. Indeed, the plaintiffs do not seriously dispute that a permanent right-of-way is reasonable here. BLM was mandated by Congress to issue permanent rights-of-way for two other counties, and given this project is subject to a single grant, setting a different term for White Pine County makes little sense.

Congress mandated permanent rights-of-way for two of the counties. See section 4(b)(2)(B) of the SNPLMA, Pub. L. No. 105-263, and section 301(b)(2) of the LCCRDA, Pub. L. No. 108-424.

Instead, the plaintiffs point to another section of FLPMA to argue that BLM has no authority to issue permanent rights-of-way at all. The plaintiffs rely on 43 U.S.C. § 1761(c), which governs "Permanent easement[s] for water systems." This section states that certain easements across National Forest Lands should be permanent. The plaintiffs conclude that FLPMA must prohibit permanent grants generally, and that this exception for forest lands is a narrow carve-out for a special type of easement. But there is no textual support for this interpretation of the statute. The text that authorizes rights-of-way says that the term must be reasonable, it says nothing about limiting BLM's authority to issue permanent grants. That Congress mandates one type of grant to be permanent does not mean that it intended to revoke an agencies' power to grant a permanent right-of-way in other situations when the circumstances warrant it. If Congress meant to expressly limit BLM's authority as the plaintiffs suggest, it could have said so.

To the extent that there is any ambiguity as to whether BLM has authority to issue permanent rights-of-way under § 1764, the agency's reasonable interpretation would prevail. BLM's regulations interpret § 1764 as allowing permanent grants so long as they are reasonable under the circumstances. Given there is no express language in the statute to suggest that BLM does not have this authority, BLM's interpretation is entitled to deference. This is particularly true here given BLM's longstanding interpretation of its authority to issue these grants, as well as the legislative history, which suggests that permanent grants are permissible. I thus reject this challenge.

See Chevron, U.S.A., Inc. v. Natural Res. Def. Council, 467 U.S. 837, 843-44 (1984).

In the preamble to the final rule promulgating the regulations at issue, BLM stated that the grant of a right-of-way in perpetuity may be appropriate in "a variety of circumstances," and that it "frequently issue[s] perpetual grants to governmental entities for permanent facilities such as county roads." 70 Fed. Reg. 29,970, 21,010 (Apr. 22, 2005).

A House report on Section 504 of FLPMA states, "The requirement that the term of a right-of-way be 'limited to a reasonable term' does not prevent the issuance of rights-of-way for indefinite terms . . . ." H.R. Rep. No. 94-1163, at *22 (May 15, 1976).

iv. FLPMA claim for failure to prevent unnecessary and undue degradation and damage to the environment

White Pine County argues that BLM violated its FLPMA mandate to "prevent unnecessary or undue degradation" to the lands it manages. The County acknowledges, however, that neither FLPMA nor its implementing regulations define "unnecessary or undue degradation." Such broad language, in conjunction with FLPMA's multiple use mandate, gives BLM extensive discretion in interpreting what environmental impacts are unnecessary or undue. BLM expressly incorporated in its discussion of environmental impacts and mitigation measures its determination that the project did not cause unnecessary or undue degradation. I defer to this determination.

ECF No. 98 at 47-48 (citing 43 U.S.C. § 1732(a) & (b)).

See, e.g., Gardner v. Bureau of Land Mgmt., 638 F.3d 1217, 1222 (9th Cir. 2011).

AR 188174.

v. FLPMA claim for failure to ensure compliance with air quality standards

White Pine County argues that the project violates BLM's FLPMA obligation to comply with federal and state air quality standards. While the County does not specify what standards the project violates, it contends that BLM failed to sufficiently explore the question by choosing not to evaluate impacts to air quality for water drawdowns under ten feet or after 200 years. BLM responds that it prepared a model of dust emissions based on future groundwater pumping and found that dust emissions would not violate air quality laws. This satisfied BLM's burden at this point to assess possible future compliance issues with FLPMA. As discussed above, it was within BLM's discretion to decide that impacts of groundwater withdrawal under ten feet or beyond 200 years were too minimal or speculative to yield meaningful insight. And BLM adds that it will conduct more robust analysis as part of its COM Plan and future NEPA analyses.

See ECF No. 98 at 51-52.

ECF No. 124 at 63.

Id.

vi. FLPMA claim for failure to ensure SNWA's financial capability to construct, operate, maintain, and terminate its project

White Pine County argues that BLM violated FLPMA by failing to establish that SNWA "has demonstrated the financial capability to construct, operate, and maintain" the project. The County concedes that the EIS contains an analysis of SNWA's financial capability, but contends that the analysis underestimates the project's costs for monitoring, management, and mitigation, thus rendering the financial capability estimate infirm.

ECF No. 98 (citing 43 U.S.C. § 1764(j)).

BLM responds that its duty under FLPMA was only to ensure it was "satisfied that [SNWA] has the technical and financial capability to construct the project," which SNWA demonstrated with a report from a financial consultant. The consultant specifically found that SNWA has the "flexibility and capability" to cover the costs of management and mitigation. In its response, SNWA notes that it added a 30 percent "monitoring, management, and mitigation" factor to account for these costs. White Pine County does not address the issue in its reply. BLM was reasonable in concluding that SNWA has the financial capability to construct and manage the project, especially given that SNWA specifically budgeted a significant amount for management costs. / / / / / / / / / / / /

ECF No. 107 at 74.

Id.

ECF No. 110 at 72.

D. Challenges under the National Historic Preservation Act

i. Background

Section 106 of the National Historic Preservation Act (NHPA) requires federal agencies to consider the potential effects of federal actions on historic properties. Section 106 requires BLM to "take into account the effect of [an] undertaking on any district, site, building, structure, or object that is included in or eligible for inclusion in the National Register [of Historic Places]." Like NEPA, Section 106 of the NHPA "is a stop, look, and listen provision that requires each federal agency to consider the effects of its programs."

When the parties briefed this case, the relevant provisions were at 16 U.S.C. § 470f (2013). But in December 2014, NHPA Section 402 was moved to Title 54 of the U.S. Code, and the specific provision now is found at 54 U.S.C. § 306108.

Muckleshoot Indian Tribe v. U.S. Forest Serv., 177 F.3d 800, 805 (9th Cir. 1999).

Agencies must also "consult with any Indian tribe . . . that attaches religious and cultural significance to historic properties that may be affected by an undertaking." And it must "provide[] the Indian tribe . . . a reasonable opportunity to identify its concerns about historic properties, advise on the identification and evaluation of historic properties, including those of traditional religious and cultural importance, articulate its views on the undertaking's effects on such properties, and participate in the resolution of adverse effects."

Id.

An agency must "make a reasonable and good faith effort" to identify historic properties within a project's area of potential impact. If the agency finds that historic or culturally significant sites may be affected, it must solicit the views of the various interested parties. The agency then considers whether there is an adverse effect, and if so, engages in further consultation about resolving those harms. Similar to NEPA, the NHPA's regulations permit an agency to "use a phased process to conduct identification and evaluation efforts" or to "defer final identification and evaluation of historic properties" under certain circumstances, including where the alternatives under consideration involve "large land areas" or "corridors."

ii. Whether BLM violated the NHPA's Section 106 consultation requirements

The NHPA implementing regulations require BLM, at all stages of the section 106 process, to consult with tribes that "attach[] religious and cultural significance to historic properties that may be affected by an undertaking." Further, "[c]onsultation should commence early in the planning process, in order to identify and discuss relevant preservation issues," and "must recognize the government-to-government relationship between the Federal Government and Indian tribes."

Id. § 800.2(c)(2)(ii)(C).

The plaintiffs first argue that BLM failed to adequately consult with the tribes because the agency does not yet have "adequate information about water appropriations, or the location of the pipeline and its pumping stations." This argument rehashes the same challenges that I reject above. There is nothing in the NHPA or NEPA that precludes BLM from approving the pipeline project in phases. BLM cannot be faulted for consulting with the tribes before having more data because it is approving the first phase of this project without the benefit of all of the evidence it needs to decide whether to approve future phases of the project. This approach is reasoned and thus not arbitrary. And the regulations and relevant case law support BLM's approach on this point.

36 C.F.R. § 800.14(b)(ii) (programmatic agreements appropriate "[w]hen effects on historic properties cannot be fully determined prior to approval of an undertaking"); Honolulu-traffic.com., 742 F.3d at 1233-34 (approving phased approach to identification of burial sites where "exact route and placement of the support columns had not yet been determined"); Te-Moak Tribe of W. Shoshone of Nev. v. U.S. Dep't of Interior, 608 F.3d, 592, 610 (9th Cir. 2010) (for the same reason that "a phased exploration project in some circumstances can be fully approved without all the details of the separate phases" under NEPA, the court "reach[ed] the same conclusion in the NHPA context").

The plaintiffs also argue that BLM's single face-to-face meeting with the Goshute tribe was insufficient consultation. But the record indicates that BLM did much more than that. BLM invited this tribe to engage in formal consultation five years prior to the pipeline's approval. Both BLM's Field Manager and Nevada State Director engaged in consultation at different points, as did BLM's Project Manager, Ethnographer, and Associate Field Manager responsible for the Project. BLM, through various agency officials, attended at least six meetings on the Goshute Tribe's reservation while considering the project. BLM's consultation was much more robust than the efforts other courts have found insufficient.

AR 189782-86.

AR 189814. The Goshute tribe also contends that BLM acted arbitrarily when it did not designate certain tribes as "cooperating agencies." But BLM had discretion whether to designate the tribe with this status, and the tribe has not offered any analysis or explanation as to why this decision was arbitrary.

See, e.g., Quechan Tribe of the Fort Yuma Indian Reservation v. U.S. Dep't of Interior, 755 F. Supp. 2d 1104 (S.D. Cal. 2010) (finding insufficient consultation because the agency did not meet with the tribe until after the project was approved, never invited the tribe to engage in government-to-government consultation with anyone at the field manager level or higher, did not engage in any meetings with the tribal council, and repeatedly rebuffed requests for consultation).

iii. Whether BLM failed to properly identify impacts on cultural resources

BLM is required to engage in a good faith effort to identify cultural resources that might be impacted by the project and to consult with the tribes about them. BLM did that. BLM created a 137-page cultural resources inventory and a 147-page ethnographic assessment for this project. The authors of the ethnographic assessment relied on interviews with tribe members and site visits in 2008 and 2009 attended by the Goshute Tribe's representatives, as well as prior studies and scholarly references. The ethnographers prepared a report, successive drafts of which were circulated among identified Indian tribes. Indeed, the Goshute Tribe passed a resolution endorsing the report's identification of sacred sites. BLM thus engaged in a good-faith attempt to identify relevant cultural sites and consult with the tribes about how best to protect them.

AR 220338-474; AR 190410-557.

See AR 131003-06 (describing methodology for Weidlich & Molenaar ethnographic assessment and tribal participation in process).

AR 131005, 23979.

iv. Whether BLM violated reserved tribal water rights

Under Winters v. United States, 207 U.S. 564 (1908), when the United States sets aside an Indian reservation, it impliedly reserves water for the reservation. The Goshute tribe contends that BLM failed to adequately consider how SNWA's pumping will impact its federally-reserved water.

The tribe fails to point to any specific water rights that might be impacted by the pipeline. And BLM conducted a thorough review of potential impacts to federal water reserves. BLM inventoried reserved water rights and identified the rights that had been adjudicated in Nevada and Utah. BLM explained in the EIS that the state databases do not necessarily include unadjudicated federal reserved water rights, and therefore the location and quantities of some rights are unknown. But BLM analyzed the impacts to water resources—including an estimation of any unidentified reserved water rights—from groundwater pumping and mitigation to minimize those impacts.

BLM offers evidence that the pipeline is not expected to have any impact on the tribe's water resources. AR 130104. The tribe cites some letters from BLM, but they are unhelpful. In one, BLM merely explained that future water adjudications were not within the scope of its EIS. In the other, the agency explained that its EIS was not necessarily coextensive with SNWA's water stipulations. Neither of these suggests that BLM failed to consider federal water reserves.

The Goshute Tribe also argues that BLM failed to consider impacts to the tribe's aboriginal hunting and fishing rights. But the EIS discusses the historic use of the area by the Goshute Tribe and other tribes for hunting, fishing, and pine nut gathering. And it discusses that the pipeline could affect their traditional uses of land within the analysis area. The agency thus considered these issues, which is all that is required here. Finally, the tribe waived its right to bring challenges based on reserved water rights, so it cannot bring that claim now.

ECF No. 62 at 2 ("Because plaintiffs have clarified they are not asserting independent claims based on AIRFA or reserved water rights, I deny as moot defendants' motion to dismiss counts thirteen and fourteen."). --------

III. CONCLUSION

IT IS THEREFORE ORDERED that the plaintiffs' motions for summary judgment (ECF Nos. 87, 93, 97, and 99) are GRANTED IN PART AND DENIED IN PART as set forth above.

IT IS FURTHER ORDERED that the defendants' motions for summary judgment (ECF Nos. 107 and 110) are GRANTED IN PART AND DENIED IN PART as set forth above.

IT IS FURTHER ORDERED that the identified issues are remanded to BLM. The clerk of the court is directed to close this case.

DATED this 23rd day of August, 2017.

/s/_________

ANDREW P. GORDON

UNITED STATES DISTRICT JUDGE


Summaries of

Ctr. for Biological Diversity v. U.S. Bureau of Land Mgmt.

UNITED STATES DISTRICT COURT DISTRICT OF NEVADA
Aug 23, 2017
Case No. 2:14-cv-00226-APG-VCF (D. Nev. Aug. 23, 2017)
Case details for

Ctr. for Biological Diversity v. U.S. Bureau of Land Mgmt.

Case Details

Full title:CENTER FOR BIOLOGICAL DIVERSITY, Plaintiff, v. UNITED STATES BUREAU OF…

Court:UNITED STATES DISTRICT COURT DISTRICT OF NEVADA

Date published: Aug 23, 2017

Citations

Case No. 2:14-cv-00226-APG-VCF (D. Nev. Aug. 23, 2017)

Citing Cases

W. Watersheds Project v. U.S. Dep't of the Interior

Norton v. S. Utah Wilderness All., 542 U.S. 55, 59 (2004) (citing 43 C.F.R. § 1601.0-5(k) (2003)). “While…