Opinion
April 5, 1999
Appeal from the Supreme Court, Westchester County (Nicolai, J.).
Ordered that the judgment is affirmed insofar as appealed and cross-appealed from, without costs or disbursements.
The plaintiff and the defendants entered into a construction contract whereby the plaintiff agreed to be the subcontractor for the defendants, acting as general contractors, on a project known as the Half Moon Construction project. One of the contract's provisions required that the general contractor be paid by the owner before being required to pay the subcontractor, the so-called "pay-when-paid" provision. Another provision required the subcontractor to bring any action seeking payment within 90 days after the work had been completed. After the construction work was completed, the defendants submitted a requisition totalling $541,016.16. The owner then filed for bankruptcy. Following the bankruptcy, the owner made three payments, to the defendants totaling $122,000. None of this money was ever paid to the plaintiff.
Parties to a contract may agree to limit the period of time in which an action must be commenced to a shorter time than that otherwise provided by the applicable Statute of Limitations ( see, Kassner Co. v. City of New York, 46 N.Y.2d 544, 550-551; Krohn v. Felix Indus., 226 A.D.2d 506; Wayne Drilling Blasting v. Felix Indus., 129 A.D.2d 633, 634). "`Absent proof that the contract is one of adhesion or the product of overreaching, or that [the] altered period is unreasonably short, the abbreviated' period of limitation will be enforced'" ( Wayne Drilling Blasting v. Felix Indus., supra, at 634; see, Timberline Elec. Supply Corp. v. insurance Co., 72 A.D.2d 905, 906, affd 52 N.Y.2d 793). However, where two provisions of a contract conflict, the contract must be resolved against "the party who drew the contract ( see, Matter of Zaremba v. Interface Flooring Sys., 195 A.D.2d 471, 473; Wing v. Wing, 112 A.D.2d 932, 933-934).
In the instant case, the 90-day period of limitations, while freely agreed to by the parties, is inconsistent with the pay when-paid clause, and is unenforceable since it unreasonably deprives the plaintiff of a course' of action. Under the pay when-paid clause, the plaintiff could not maintain its action against the general contractor until the owner paid the "general contractor. However, by that time, due' to the bankruptcy of the owner, the 90-day limit would have expired. Moreover, if the two clauses are given effect, and the plaintiff brought an action to recover the value of the work performed within the 90-day limit, the action would have failed by virtue of the nonoccurrence of the condition that payment be made by the owner to the general : contractor. Therefore, interpreting the contract against the defendants, we find that the 90-day period of limitations is not applicable in this case, and that the action was timely commenced under the applicable Statute of Limitations.
We further find that the court properly determined that the amount of damages owed to the plaintiff was the same percentage of the total amount it sought under the subcontract as that received by the defendants from the owner under the general contract, with interest to be awarded from the date of the final payment by the owner to the defendants.
The parties' remaining contentions are without merit.
O'Brien, J. P., Ritter, Thompson and Joy, JJ., concur.