128 Hester LLC v. N.Y. State Div. of Hous. & Cmty. Renewal

Supreme Court, Appellate Division, First Department, New York.
Jan 31, 2017
146 A.D.3d 706 (N.Y. App. Div. 2017)

Opinion

01-31-2017

In re 128 HESTER LLC, Petitioner–Appellant, v. The NEW YORK STATE DIVISION OF HOUSING & COMMUNITY RENEWAL, et al., Respondents–Respondents.

Klein Slowik PLLC, New York (Daniel J. Schneider of counsel), for appellant. Mark F. Palomino, New York (Robert Ambaras of counsel), for New York State Division of Housing and Community Renewal, respondent. John D. Gorman, New York, for Hun Sui Chu, Kok Hong The, Eng Kam Li, Wang Ai Yu, Ji De Yang, Jian Qing Han, Alice Jean, John Jean, Duan Liang Chen and Chai Oi Hoy, respondents.


Klein Slowik PLLC, New York (Daniel J. Schneider of counsel), for appellant.

Mark F. Palomino, New York (Robert Ambaras of counsel), for New York State Division of Housing and Community Renewal, respondent.

John D. Gorman, New York, for Hun Sui Chu, Kok Hong The, Eng Kam Li, Wang Ai Yu, Ji De Yang, Jian Qing Han, Alice Jean, John Jean, Duan Liang Chen and Chai Oi Hoy, respondents.

RICHTER, J.P., ANDRIAS, SAXE, GESMER, JJ.

Order and judgment (one paper) of Supreme Court, New York County (Carol E. Huff, J.), entered April 7, 2015, which granted respondent New York State Division of Housing and Community Renewal's (DHCR) motion for leave to file a surreply, denied the petition to annul DHCR's determination, dated October 17, 2013, denying the petitions for administrative review and directing petitioner to pay respondents tenants demolition stipends and relocation costs in consequence of the demolition of the subject building, and dismissed the proceeding brought pursuant to CPLR article 78, unanimously affirmed, without costs.

The article 78 court providently exercised its discretion in granting DHCR leave to file a surreply to rebut averrals in petitioner's pleadings (see Pena– Vazquez v. Beharry, 82 A.D.3d 649, 649, 919 N.Y.S.2d 336 [1st Dept.2011] ).

Petitioner was afforded due process at the various stages of this proceeding (see Matter of Beck–Nichols v. Bianco, 20 N.Y.3d 540, 559, 964 N.Y.S.2d 456, 987 N.E.2d 233 [2013] ; Matter of Daxor Corp. v. State of N.Y. Dept. of Health, 90 N.Y.2d 89, 659 N.Y.S.2d 189, 681 N.E.2d 356 [1997], cert. denied 523 U.S. 1074, 118 S.Ct. 1516, 140 L.Ed.2d 669 [1998] ).

The agency determination has a rational basis in the record (see Matter of Partnership 92 LP & Bldg. Mgt. Co., Inc. v. State of N.Y. Div. of Hous. & Community Renewal, 46 A.D.3d 425, 428, 849 N.Y.S.2d 43 [1st Dept.2007], affd. 11 N.Y.3d 859, 873 N.Y.S.2d 247, 901 N.E.2d 740 [2008] ). The record shows that, by the time petitioner purchased the building in August 2007, it was already in extremely poor physical condition, settling unevenly into its foundation and leaning six inches out of plumb, its internal steel support columns also leaning precariously, and wooden floor joists rotten and damaged by termites. Although petitioner undertook emergency shoring work, allegedly spending $100,000, the building continued to deteriorate and lean farther out of plumb, its demise hastened by vibrations from construction work on an 18–story hotel on an adjacent lot. Petitioner took no action for two years, until the building had deteriorated beyond repair, despite last-ditch efforts ordered by the Department of Buildings (DOB) in the summer of 2009.

Petitioner cannot escape responsibility for the building's precarious condition when acquired, since the condition was documented in outstanding DOB violations, and "the need to make ... repairs could have been anticipated" before the purchase (Eyedent v. Vickers Mgt., 150 A.D.2d 202, 205, 541 N.Y.S.2d 210 [1st Dept.1989] ). Similarly, to the extent the deterioration was accelerated by work on the adjacent hotel project, it was incumbent upon petitioner, as landlord, to take steps to ameliorate it, including through stop work orders. As landlord, petitioner was obligated to take reasonable steps to protect the building from the effects of the work next door, regardless of whether there was any overlap in ownership interests in the two properties (see Park W. Mgt. Corp. v. Mitchell, 47 N.Y.2d 316, 327, 418 N.Y.S.2d 310, 391 N.E.2d 1288 [1979], cert. denied 444 U.S. 992, 100 S.Ct. 523, 62 L.Ed.2d 421 [1979] ). DHCR thus rationally concluded that petitioner "allow[ed] the building to deteriorate to the point where it would fall down" (Eyedent, 150 A.D.2d at 204, 541 N.Y.S.2d 210 [internal quotation marks omitted] ), warranting the award of demolition stipends and relocation costs (see 9 NYCRR 2524.5 [a][2][ii][a], 2524.5[ii][b][3] ).

DHCR Operational Bulletin 2009–1 is not a "rule" for purposes of the State Administrative Procedure Act (see id. § 102[2][a][i], [b][iv] ), but merely develops the parameters for calculation of the demolition stipend, as expressly provided for in the Rent Stabilization Code (see 9 NYCRR 2524.5 [a] [2][ii][a], 2524.5[ii][b][3], 2527.11).

We have considered petitioner's remaining contentions and find them unavailing.


Summaries of

128 Hester LLC v. N.Y. State Div. of Hous. & Cmty. Renewal

Supreme Court, Appellate Division, First Department, New York.
Jan 31, 2017
146 A.D.3d 706 (N.Y. App. Div. 2017)
Case details for

128 Hester LLC v. N.Y. State Div. of Hous. & Cmty. Renewal

Case Details

Full title:In re 128 HESTER LLC, Petitioner–Appellant, v. The NEW YORK STATE DIVISION…

Court:Supreme Court, Appellate Division, First Department, New York.

Date published: Jan 31, 2017

Citations

146 A.D.3d 706 (N.Y. App. Div. 2017)
46 N.Y.S.3d 85
2017 N.Y. Slip Op. 581

Citing Cases

128 Hester LLC v. N.Y.S. Div. of Hous. & Cmty. Renewal

Judgment, Supreme Court, New York County (Gerald Lebovits, J.), entered on or about January 19, 2020, denying…

128 Hester LLC v. N.Y. State Div. of Hous. & Cmty. Renewal

entered on or about January 19, 2020, denying the petition to annul determinations of respondent New York…