Current with legislation from the 2023 Regular and Special Sessions signed by the Governor as of November 21, 2023.
Section 134.065 - Permit Approval or Denial(a) On the basis of a complete application for a surface coal mining and reclamation permit or a revision or renewal of a permit, as required by this chapter, the commission shall grant, require modification of, or deny a permit application.(b) The commission shall notify the applicant of its decision in writing within a reasonable time as set by the commission.(c) An applicant for a permit or a permit revision has the burden of establishing that the application complies with this chapter.(d) Not later than the 10th day after the date the commission grants a permit, the commission shall notify the county judge in the county in which the land to be affected is located that a permit has been issued and shall describe the location of the land.Tex. Nat. Res. Code § 134.065
Added by Acts 1995, 74th Leg., ch. 76, Sec. 12.02(a), eff. 9/1/1995.