Current with legislation from the 2023 Regular and Special Sessions signed by the Governor as of November 21, 2023.
Section 2253.046 - Notice Required for Claim for Payment of Retainage(a) To recover in a suit under Section 2253.073 on a payment bond for a claim for payment of retainage, a payment bond beneficiary whose contract with a prime contractor or subcontractor provides for retainage must mail written notice of the claim to the prime contractor and the surety on or before the 90th day after the date of final completion of the public work contract.(b) The notice shall consist of a statement of:(1) the amount of the contract;(3) the outstanding balance.(c) Notice of a claim for payment of retainage is not required if the amount claimed is part of a prior claim made under this subchapter.Tex. Gov't. Code § 2253.046
Added by Acts 1993, 73rd Leg., ch. 268, Sec. 1, eff. 9/1/1993.