Current with changes through the 2024 First Special Legislative Session
Section 46-1662 - Periodic inspections; when; department; powers and duties(1) During the construction, reconstruction, enlargement, alteration, breach, removal, or abandonment of any dam, the department may make periodic inspections for the purpose of ascertaining compliance with the approved plans and specifications. The department shall require the owner to direct the design engineer to provide adequate supervision during construction, reconstruction, enlargement, alteration, breach, removal, or abandonment and to provide sufficient information to enable the department to determine that conformity with the approved plans and specifications is being attained.(2) If, after any inspection or investigation, during the construction, reconstruction, enlargement, alteration, breach, removal, or abandonment of a dam or at any time prior to issuance of an approval to operate, it is found by the department that modifications or changes are necessary to ensure the safety of the dam, the department shall order the owner to revise his or her plans and specifications. The owner may, pursuant to section 46-1645, request an independent consulting board to review the order of the department.(3) If at any time during construction, reconstruction, enlargement, alteration, breach, removal, or abandonment of any dam, the department finds that the work is not being done in accordance with the approved plans and specifications, the department shall deliver a written notice of noncompliance to the owner. The notice shall be delivered by registered mail or by personal service to the owner, shall state the particulars in which the approved plans and specifications are not being or have not been complied with, and shall order immediate compliance with the approved plans and specifications. The department may order that no further work be done until such compliance has been effected and approved by the department.(4) Failure to comply with the notice delivered under subsection (3) of this section may cause revocation of application approval by the department. If compliance with the notice has not occurred within sixty days after the date of the notice, the department shall order the incomplete structure removed sufficiently to eliminate any safety hazard to life.Neb. Rev. Stat. §§ 46-1662