Section 46-1659 - Removal, breach, or abandonment of dam; design engineer; duties; department; powers
(1) Upon completion of the removal, breach, or abandonment of a dam, the design engineer shall file with the department a completion certification.
(2) Before final approval of the removal of a dam is issued, the department may inspect the site of the work and determine that all work was accomplished in substantial conformance with the application approval.
(3) Following the removal of a dam, the department may report such removal to the National Performance of Dams Program and to the National Inventory of Dams.