Wash. Rev. Code § 47.20.785

Current through the 2024 Regular Session
Section 47.20.785 - Design-build-Qualified projects

The department of transportation is authorized and strongly encouraged to use the design-build procedure for public works projects over two million dollars when:

(1) The construction activities are highly specialized and a design-build approach is critical in developing the construction methodology; or
(2) The projects selected provide opportunity for greater innovation and efficiencies between the designer and the builder; or
(3) Significant savings in project delivery time would be realized.

RCW 47.20.785

Amended by 2015SP3 c 18,§ 2, eff. 7/6/2015.
2006 c 37 § 1; 2001 c 226 § 3.

Effective date-2015 3rd sp.s. c 18: See note following RCW 47.20.780.

Findings-Purpose-2001 c 226: See note following RCW 47.20.780.