ORS § 757.308

Current through 2024 Regular Session legislation effective June 6, 2024
Section 757.308 - Requirements related to request for proposals that may result in procurement of covered project
(1) A request for proposals submitted by an electric company, as defined in ORS 757.600, for resource procurement that is subject to competitive bidding requirements adopted by the Public Utility Commission by rule and that may result in the procurement of a covered project must:
(a) Include a reference to and information regarding the requirements in ORS 757.306; and
(b) Require that a successful bidder within 30 days from the date construction begins, provide a copy of the attestation or declaration or executed project labor agreement as required under ORS 757.306.
(2) The State Department of Energy shall, upon request from the commission, provide a copy of the attestation or declaration or project labor agreement to the commission.

ORS 757.308

Added by 2022 Ch. 51, § 2

757.308 was enacted into law by the Legislative Assembly but was not added to or made a part of ORS chapter 757 or any series therein by legislative action. See Preface to Oregon Revised Statutes for further explanation.