Section 436.327 - Substantial completion defined

The project shall be deemed to have reached substantial completion upon the occurrence of the earlier of the architect or engineer issuing a certificate of substantial completion in accordance with the terms of the contract documents or the owner accepting the performance of the full contract.

§ 436.327, RSMo

L. 2002 H.B. 1403