A public utility that furnishes natural gas may petition the commission for approval of a performance-based gas purchasing plan under this section. The commission may approve a plan if it finds that:
A plan must include a mechanism through which the utility shares with its customers the difference between actual natural gas costs and the plan's benchmark costs during the term of the plan. A plan must provide details of the sharing mechanism and may include an allowed level of costs above and below the benchmark before any sharing is to take place. The commission must determine an appropriate percentage of the difference between the benchmark and actual natural gas costs to be shared between customers and the utility. The sharing mechanism shall be implemented annually under section 216B.16, subdivision 7a. Financial rewards or penalties under the plan shall not be considered in the determination of the utility's revenue requirements in a general rate case pursuant to section 216B.16.
A plan must allow for the imposition of penalties if the standard for reliability of service established in subdivision 1, clause (4), is not met.
A plan must include an evaluation process and mechanism that is reasonable and capable of supporting a full review of the utility's performance under the plan. The commission shall evaluate the various customer and utility impacts of a plan based on this evaluation process and mechanism, including the impact on customer bills over time, the impact on utility revenues, and the effectiveness of the plan in meeting the purposes contained in subdivision 1. The evaluation must occur within a reasonable time following the end of the plan.
The utility shall provide an annual report to the commission documenting its performance in meeting the requirements of the plan. Upon review of this report, the commission shall determine and approve rewards or penalties as provided in the plan.
A plan may be filed and approved within a miscellaneous tariff filing pursuant to section 216B.16. The commission may approve, reject, or modify the plan in a manner which meets the requirements of this section. An approved plan is effective for a period of not less than two years unless:
[Repealed, 1999 c 21 s 1]
[Repealed, 1999 c 21 s 1]
Minn. Stat. § 216B.167