Current through P.L. 171-2024
Section 5-30-5-6 - Selection of potential design-builders(a) The technical review committee shall select at least three (3) potential design-builders considered to be the most highly qualified to perform the required services based on the rankings of the potential design-builders. The technical review committee shall report the selection of qualified design-builders to the public agency.(b) Notwithstanding subsection (a), if only two (2) potential design-builders respond to the request for qualifications, the technical review committee may report the two (2) potential design-builders to the public agency if the technical review committee finds that both potential design-builders are qualified to perform the required services.(c) If: (1) only one (1) potential design-builder responds to the request for qualifications; or(2) only one (1) of the potential design-builders responding to the request for qualifications is qualified to perform the required services; the public agency may not use the design-build contracting method authorized under this chapter, unless the governing body of the public agency adopts a resolution expressly authorizing the public agency to send the one (1) potential designer-builder referred to in subdivision (1) or (2) a request for proposal under IC 5-30-6. The governing body must adopt the resolution at a public meeting for which public notice has been provided.
As added by P.L. 74-2005, SEC.1.