Current through P.L. 171-2024
Section 14-26-8-43 - New assessments where no contract let(a) If the surveyor is unable to let a contract and construct the proposed improvement for the estimated cost of construction, the surveyor shall report the fact to the court.(b) The court shall immediately order a new assessment of benefits and damages if requested in writing by at least two-thirds (2/3) of the original petitioners.(c) If the order for a new assessment is made:(1) the procedure provided for following the making of the original assessment shall be followed with respect to the new assessment and subsequent actions; and(2) the landowners have the same right to remonstrate and appeal as is provided for original assessments.Pre-1995 Recodification Citation: 13-2-18-16.
As added by P.L. 1-1995, SEC.19.