Current through P.L. 171-2024
Section 13-20-10.5-1 - Department approval(a) A person may not after June 30, 2011, start:(1) construction of:(A) a biomass anaerobic digestion facility; or(B) a biomass gasification facility; or(2) expansion of: (A) a biomass anaerobic digestion facility; or(B) a biomass gasification facility; without obtaining prior approval of the department.
(b) A person who proposes to construct or expand a biomass anaerobic digestion facility or a biomass gasification facility on the premises of a confined feeding operation must obtain the prior approval required under subsection (a) through the approval process for confined feeding operations under IC 13-18-10 and rules implementing that chapter.Added by P.L. 189-2011, SEC. 13, eff. 7/1/2011.