Haw. Rev. Stat. § 672E-9

Current through the 2024 Legislative Session
Section 672E-9 - Additional construction defects

A construction defect discovered after the notice of claim is served may not be alleged in an action until the claimant has given the contractor:

(1) A written notice of claim regarding the alleged defect under section 672E-3; and
(2) An opportunity to repair the construction defect or reject the notice of claim under section 672E-4.

HRS § 672E-9

L 2004, c 119 , pt of §2 .