Whenever the authority undertakes or executes any action or contract involving the closure, maintenance, decommissioning or conversion of any nuclear power plant constructed by a utility corporation which has not entered commercial operation, the authority shall, in order to ensure that neither the authority nor its customers shall bear any of the costs associated therewith, provide for the full recovery from such corporation, its successors or assigns of:
In no event shall the authority recover any costs or damages related to such actions or contracts from any of its customers other than such corporation its successors or assigns.
N.Y. Pub. Auth. Law § 1005-A