Va. Code § 43-8

Current with changes from the 2024 legislative session through ch. 845
Section 43-8 - Sufficiency of memorandum, affidavit and notice required by section 43-7

The memorandum, affidavit and notice required by § 43-7 shall be sufficient if substantially in form and effect as follows:

Memorandum for Mechanic's Lien Claimed by Subcontractor.

Name of owner: ___________________________________________________________________________

Address of owner: ___________________________________________________________________________

Name of general contractor (if any): ___________________________________________________________________________

Name of claimant: ___________________________________________________________________________

Address of claimant: ___________________________________________________________________________

Contractor license or certificate number of claimant

(if applicable): ___________________________________________________________________________

Issuance date of license or certificate

(if applicable): ___________________________________________________________________________

Expiration date of license or certificate

(if applicable): ___________________________________________________________________________

If no contractor license or certificate number is included, the claimant certifies that such a valid license or certificate is not required by law for the work done for which the benefit of a lien is claimed.

1. Type of materials or services furnished: ___________________________________________________________________________

___________________________________________________________________________

2. Amount claimed: $___________________________________________________________________________

If any part of the Amount claimed is not due as of the date of this mechanic's lien, identify the date or event upon which it will be due and the sum(s) to which the due date(s) or event(s) apply: ___________________________________________________________________________

3. Type of structure on which work done or materials furnished: ___________________________________________________________________________

___________________________________________________________________________

4. Brief description and location of real property: ___________________________________________________________________________

___________________________________________________________________________

5. Date from which interest on above amount is claimed:

Date: _________________________

It is the intent of the claimant to claim the benefit of a lien.

___________________________________________________________________________ (Name of claimant).

Affidavit.

State of Virginia,

County (or city) of __________________________________ to wit:

I, _____________________________ (notary or other officer) for the county (or city) aforesaid, do certify that ______________, claimant, or ________________, agent for claimant, this day made oath before me in my county (or city) aforesaid that __________________________ is justly indebted to claimant in the sum of ______________ dollars, for the consideration stated in the foregoing memorandum, and that the same is payable as therein stated.

Given under my hand this the ______ day of ____________, 20___.

_______________________ (Notary Public or Magistrate, et cetera.)

Notice.

To _______________________ (owner).

You are hereby notified that ____________________ (general contractor) is indebted to me in the sum of ________________ dollars ($__________) with interest thereon from the __________ day of __________, 20___, for work done (or materials furnished, as the case may be,) in and about the construction (or removal, etc.,) of a ____________________________ (describe structure, whether dwelling, store, or etc.,) which he has contracted to construct (or remove, etc.,) for you or on property owned by you in the county (or city) of _____________, and that I have duly recorded a mechanic's lien for the same.

Given under my hand this the ________________ day of ___________, 20_____.

____________________________ (Subcontractor).

Va. Code § 43-8

Code 1919, § 6428; 1968, c. 568; 2007, c. 504; 2013, c. 293; 2019, c. 243.
Amended by Acts 2019 No. 243, § 1, eff. 7/1/2019.
Amended by Acts 2013 No. 293, § 1, eff. 7/1/2013.