Section 49-1211 - Project delivery methods

The authority may provide for the development or operation of water-related facilities using a variety of project delivery methods and forms of agreement. The methods may include:

1. Predevelopment agreements leading to other implementing agreements.
2. A design-build agreement.
3. A design-build-maintain agreement.
4. A design-build-finance-operate agreement.
5. A design-build-operate-maintain agreement.
6. A design-build-finance-operate-maintain agreement.
7. A concession agreement providing for the private partner to design, build, operate, maintain, manage or lease a water-related facility.
8. Any other project delivery method or agreement or combination of methods or agreements that the authority determines are reasonable or necessary to carry out the authority's purposes.