Wash. Admin. Code § 392-344-155

Current through Register Vol. 24-16, August 15, 2024
Section 392-344-155 - Final acceptance of project by architect/engineer

Upon final completion of the project by contractor(s), the architect/engineer shall inspect the project to determine compliance with the construction documents. The architect/engineer, upon determining that the project has been completed satisfactorily, shall make such recommendation through the issuance of a certificate of completion to the school district board of directors. Separate certificates of completion shall be written for each contract awarded. Certificates of completion shall provide a statement of work completed including the gross square footage of new and/or modernized construction per WAC 392-343-019.

Wash. Admin. Code § 392-344-155

Statutory Authority: RCW 28A.525.020. 06-16-032, amended and recodified as § 392-344-155, filed 7/25/06, effective 8/25/06; 98-19-141, § 180-29-155, filed 9/23/98, effective 10/24/98. Statutory Authority: RCW 28A.47.830. 83-21-067 (Order 12-83), § 180-29-155, filed 10/17/83.